+15 working days on the project's default calendar. The programme's own finish, as the scheduling tool shows it. No contractual completion milestone was chosen at upload, so none is measured.
Full activity listings and the complete delay register are in
the accompanying Excel appendix.
Disclosures
Analytical tool output — not expert determination
This report is automatically generated from the uploaded schedule file(s). It is an analytical aid — not an expert determination, legal advice, or a certified forensic delay analysis.
Float and criticality are the source scheduling tool's own, as recorded in the file. The tool runs its own calendar-aware critical-path pass to fill a gap where the source recorded no float on incomplete work, and to measure change between two schedules. That pass is an analytical recompute, not a substitute for re-scheduling in P6 or MS Project: it does not level resources, force Expected Finish or imposed-finish dates, or work at sub-day precision. It cannot determine contractual excusability.
Figures should be reviewed by a qualified delay analyst before being relied upon in formal contract correspondence or dispute proceedings. Nothing in this report should be construed as a legal opinion or expert witness statement.
Traced critical path differs from stored flag on 83 activities
An independent forward/backward pass on the update schedule produced a different critical-path set to the file's stored Activity.is_critical flags on 83 activities. Common causes: stale total-float values (schedule not recalculated after the last edit), retained-logic vs progress-override calculation mode, or constraint-driven criticality the V1 trace does not model. The engine used the traced path for every delay attribution downstream of this section — divergences therefore propagate into the delay register, the criticality flags on specific events, and the isolated contribution figures. Review the divergence before relying on the numbers.
No concurrent delay detected (Society of Construction Law Delay and Disruption Protocol, 2nd Edition (2017) methodology)
No concurrent delay periods were detected in this comparison, so the concurrency methodology did not affect the engine-attributed delay figure. The Society of Construction Law Delay and Disruption Protocol, 2nd Edition (2017) methodology would have governed how any overlapping critical delays net. An alternative methodology (Malmaison 'first in time' approach (Henry Boot v Malmaison [1999] 70 ConLR 32)) is available; with no concurrent periods here it would give the same figure, but the choice can matter on updates where critical delays overlap.
For the project director
Brief
Severity-coded status headlines, top risks, what to act on.
01
Executive Summary
The project finish date has moved by fifteen working days, driven primarily by duration increases in substructure activities and a delay in the building control submission. This movement is significant as the schedule reports eighty activities with negative float, indicating that the programme is currently unable to deliver key milestones, including Practical Completion, on their planned dates. The reliability of these figures is further compromised by a critical divergence between the traced critical path and the stored flags on eighty-three activities, as noted in the DCMA 14-Point assessment. The reader should review the critical path divergence disclosure and the milestone deliverability findings to verify the integrity of the schedule logic.
02
What happened · Why · Where to investigate
Programme finish movement:15 working daysThe only delay figure is the programme finish movement; the panel below splits it into activity-level drivers and topology signals — diagnostics, not competing delay totals.
The programme finish movement of fifteen working days stands as the authoritative delay figure for this comparison period. The table below details the activity-level drivers—duration changes, progress shortfalls, and added scope—as a structural signal of where pressure built up, rather than a summed project delay total. Because each activity is measured independently, parallel paths and float-absorbed slip are included in these categories without inflating the final movement figure. The topology section identifies where the schedule was rewired between baseline and update, serving as a direction-of-travel signal rather than an isolated working-day impact, which would require a calendar-aware CPM pass per event. Readers should focus their investigation on the Superstructure package, where logic edits were recorded.
Quantified drivers (working days by category)
Category
Events
Working days
Duration changes
3
15 working days
Progress shortfall
1
4 working days
Added scope (upper bound)
1
14 working days
Top 1 WBS packages for topology edits
WBS package
Events
Logic
Constraint
Calendar
Superstructure
1
1
0
0
03
Critical-path stability
Critical-path membership churned 79% this update
79% of the critical-path membership turned over between the two submissions (72 entered, 0 left). A critical path normally drifts slowly as work completes; a large single-update turnover reflects a materially re-shaped programme.
This states the mechanical evidence in the file only. A legitimate re-plan and an undisclosed re-shaping of float are indistinguishable here, so no intent is inferred — review the flagged activities directly. The full entered / left / slipping lists are in the Excel export.
04
Key Milestones
Milestones compared:2Baseline vs current forecast finish for every milestone that exists on both schedules.
The contractual and progress milestones detected on the two schedules, with the calendar-day variance between their forecast finish dates.
Only milestones present on both sides of the comparison are shown — one-sided entries are scope moves that would make the variance column unreadable if included.
2 milestones appeared on only one side of the comparison and are omitted here — see the Scope Changes section for added/removed activities and the Key Milestones sheet in the Excel appendix for the full per-schedule list.
Variance is shown in calendar days (consistent with how EOT claims are commonly stated) so the figure matches the way the contract will evaluate it.
Key milestones — baseline vs current
Milestone
Baseline forecast finish
Current forecast finish
Current actual finish
Variance
Current float
On critical path
Fit-out complete
2028-03-07
2028-03-28
—
+21 days
-15 wd
Yes
Practical Completion
2028-06-08
2028-06-29
—
+21 days
-15 wd
Yes
05
Critical path
Activities driving the completion date in each schedule version, sourced from the stored is_critical flag on each schedule.
Where the critical path has shifted between the baseline and the update, the shift itself is often the single most important finding — it signals that delay or acceleration in one area has re-routed the critical chain through previously non-critical work.
Critical-path activities with largest baseline-vs-update variance
A diagnostic view, not the full critical path. The 15 critical-in-either activities with the largest finish variance are plotted here — the chart surfaces what moved between baseline and update, selected by the priority rule in METHODOLOGY §8 (persisted by float severity, then variance, then joined, then left). For the end-to-end critical chain from data date to project finish see the supporting views in the Narrative layer (WBS rollup, network diagram, timeline) and the comparison table there.
Each activity appears as two bars: dashed outline for the baseline plan, filled bar for the update. Fill colour encodes membership change — orange for persisted on the critical path, red for joined, grey for left.
06
Float-path risk
Near-critical paths:8sub-critical or parallel-critical, within 20 working days of the controlling path (primary driving path shown separately as rank 1; full list in the Excel appendix).
What this section answers: where else forward risk is concentrated besides the controlling chain. Each row is an alternative chain to the project endpoint that's within 20 working days of the critical path; any of them could become controlling with a small slip.
Eight float paths are identified within twenty working days of the critical path, with the cluster dominated by near-critical chains rather than zero-float sequences. The presence of multiple sub-critical paths indicates that the schedule has limited resilience, as any of these chains could become controlling with a small slip in duration or logic. The following table details the top three paths ranked by float to illustrate the immediate forward risk to the project completion date.
Top 3 float paths
#
Float
Activities
Envelope
Driving activity
Branches from
1
-27 wd
65
2026-02-16 → 2028-06-29
PRE-130 — Building control submission
—
2
-7 wd
66 (1 unique)
2026-03-06 → 2028-06-29
PRE-250 — Site security and CCTV
Path 1 at SUB-110
3
0 wd
47 (3 unique)
2026-11-03 → 2028-06-29
SUP-310 — Slab L1 formwork
Path 1 at SUP-410
Top 3 of 9 paths shown (the primary driving path plus 8 near-critical) — the full 5-path table and the float-path overlay chart are in the Narrative layer.
07
Float consumption
Float consumed:15 wd median142 activities eroding float since the baseline
What this section answers: which near-critical chains are burning float across updates — an early warning that fires before a path goes critical and shows up in the delay register. Float lost is the typical (median) like-for-like drop in total float across the chain's eroding activities, excluding any whose constraint or calendar changed (a holiday edit to the same calendar is netted out instead). It is deliberately not their sum: every activity on a float path shares that path's float, so adding their individual drops would multiply one loss by the number of activities.
142 activities eroded float since the baseline, a median of 15 working days each (2140 working days in aggregate). The median is the typical per-activity erosion; the aggregate runs far larger on a broad schedule and shouldn't be read as the delay to completion. The most-eroded near-critical path is rank 2 (driving activity PRE-250 — Site security and CCTV), down 15 wd and now at 0 working days of float.
Most-eroded near-critical paths (top 5)
#
Float now
Float lost (typical)
Activities eroding
Driving activity
2
0 wd
15 wd
66/66
PRE-250 — Site security and CCTV
1
0 wd
15 wd
65/65
PRE-130 — Building control submission
3
0 wd
15 wd
47/47
SUP-310 — Slab L1 formwork
4
0 wd
15 wd
47/47
SUP-210 — Column starter bars L3
7
2 wd
15 wd
44/44
SUP-240 — Column starter bars L4
08
Completion forecast (Earned Schedule)
Earned Schedule finish:2028-09-04Earned Schedule at the pace to date (SPIt 0.91), measured against SL-DEMO. Programme finish: 2028-06-29.
Measured against your approved baseline (SL-DEMO, finishing 2028-06-08), the work done by the data date (2026-03-06) was planned to be done by 2026-03-01: 5 days behind the baseline. That is a schedule performance index (SPIt) of 0.91. At that pace the baseline's planned duration (885 days from 2026-01-05) runs to 2028-09-04. Earned Schedule measures the rate of work (PMI Standard for EVM, 2019, §4.4); it is not a reschedule. The programme's own finish is 2028-06-29. Work is weighted by the baseline's original durations.
Completion forecast
Basis
Finish
vs programme
Programme finish
your programme
2028-06-29
—
Earned Schedule, pace to date
SPIt 0.91
2028-09-04
+67 days vs programme
To finish by the programme's own date (2028-06-29), the remaining 830 days of baseline work must be done in 846 days: a required pace (TSPIed) of 0.98 days of baseline work per day, against 0.91 achieved so far (SPIt). The required pace is within 0.10 of the pace achieved, which NDIA reads as in line with performance to date (NDIA Predictive Measures Guide, 2025, §2.6.2).
DCMA 14-Point Assessment: 7 pass, 4 fail, 3 not assessed.
DCMA items needing attention
Item
Measured
Threshold
Status
Notes
§3 Lags
5.8%
≤5% of relationships
Fail
9 of 155 relationships
§6 High Float
20.5%
≤5% of incomplete activities
Fail
27 activities with > 44 wd float
§7 Negative Float
80
0 (none allowed)
Fail
80 activities with negative float
§9 Invalid Dates
1
0 (none allowed)
Fail
1 activities with dates inconsistent with data date 2026-03-06
§10 Resources
—
Not assessed
PAM 200.1 §4.10: the IMS DID does not require resource loading, so DCMA publishes no canonical threshold for this item
§11 Missed Tasks
—
≤5% of activities with baseline finish on or before status date
Not assessed
schedule has no baseline finish dates
§14 Baseline Execution Index
0.90
≥0.95
Not assessed
9 of 10 due activities completed by data date, measured vs SL-DEMO — no approved baseline embedded in the file, so this is informational and not scored toward the 14-point total
The full 14-item scorecard (every measured value, passing items included) is in the Narrative layer; per-check offender lists are in the appendix and the Excel workbook's DCMA detail sheet.
Side-by-side comparison of the baseline and the update (SL-DEMO (data date 2026-03-06)) activity dates.
“Baseline” here means SL-DEMO (data date 2026-01-05), selected as your approved baseline. All dates are each schedule’s current forecast finish (see Methodology, Date basis).
Start and finish variances are shown in calendar days — positive values mean the update is later than the baseline.
The delay register and concurrent-delay analysis in the sections below derive from these variances.
Baseline vs update Gantt overlay
Each activity appears twice: a dashed outline bar for the baseline plan above a filled bar for the update plan. Critical-path activities are shown in red. Rows are sorted by criticality and finish variance — the activities whose dates moved most appear first.
Baseline vs update (critical path)
ID
Name
Baseline start
Baseline finish
Update start
Update finish
Start Δ
Finish Δ
Status
Critical (baseline)
Critical (update)
SUB-340
Ground beam install
2026-07-30
2026-08-17
2026-08-20
2026-09-08
+21d
+22d
not started
✓
SUB-410
Basement slab formwork
2026-08-17
2026-08-27
2026-09-08
2026-09-18
+22d
+22d
not started
✓
SUB-420
Basement slab reinforcement
2026-08-27
2026-09-15
2026-09-18
2026-10-06
+22d
+21d
not started
✓
SUP-360
Slab L2 pour
2026-11-30
2026-12-08
2026-12-21
2026-12-31
+21d
+23d
not started
✓
SUP-410
Slab L3 formwork
2026-11-30
2026-12-10
2026-12-21
2027-01-05
+21d
+26d
not started
✓
SUP-420
Slab L3 reinforcement
2026-12-10
2026-12-22
2027-01-05
2027-01-15
+26d
+24d
not started
✓
SUP-430
Slab L3 pour
2026-12-22
2027-01-04
2027-01-15
2027-01-25
+24d
+21d
not started
✓
SUP-530
Roof slab pour
2027-03-01
2027-03-09
2027-03-22
2027-04-01
+21d
+23d
not started
✓
ENV-140
Curtain wall install North elevation
2027-03-17
2027-04-09
2027-04-09
2027-04-30
+23d
+21d
not started
✓
ENV-150
Curtain wall install East elevation
2027-04-09
2027-04-30
2027-04-30
2027-05-24
+21d
+24d
not started
✓
MEP-130
Electrical containment L4-L6
2027-04-09
2027-05-06
2027-04-30
2027-05-27
+21d
+21d
not started
✓
ENV-160
Curtain wall install South elevation
2027-04-30
2027-05-24
2027-05-24
2027-06-14
+24d
+21d
not started
✓
MEP-140
Cable pulling L1-L3
2027-05-06
2027-06-03
2027-05-27
2027-06-24
+21d
+21d
not started
✓
ENV-320
Window install upper floors
2027-05-24
2027-06-09
2027-06-14
2027-06-30
+21d
+21d
not started
✓
ENV-170
Curtain wall install West elevation
2027-05-24
2027-06-14
2027-06-14
2027-07-05
+21d
+21d
not started
✓
MEP-150
Cable pulling L4-L6
2027-06-03
2027-07-01
2027-06-24
2027-07-22
+21d
+21d
not started
✓
ENV-310
External doors install
2027-06-07
2027-06-21
2027-06-28
2027-07-12
+21d
+21d
not started
✓
ENV-330
Window install lower floors
2027-06-09
2027-06-25
2027-06-30
2027-07-16
+21d
+21d
not started
✓
ENV-180
Curtain wall snagging
2027-06-14
2027-06-24
2027-07-05
2027-07-15
+21d
+21d
not started
✓
ENV-340
Glazing and seals
2027-06-25
2027-07-07
2027-07-16
2027-07-28
+21d
+21d
not started
✓
MEP-160
Distribution boards
2027-07-01
2027-07-19
2027-07-22
2027-08-09
+21d
+21d
not started
✓
MS-ENV-END
Envelope watertight
2027-07-07
2027-07-07
2027-07-28
2027-07-28
+21d
+21d
not started
✓
MEP-170
Lighting wiring rough-in
2027-07-19
2027-08-12
2027-08-09
2027-09-03
+21d
+22d
not started
✓
MEP-180
Power outlet rough-in
2027-08-12
2027-09-08
2027-09-03
2027-09-29
+22d
+21d
not started
✓
FIT-110
Stud partition L1
2027-08-16
2027-09-02
2027-09-07
2027-09-23
+22d
+21d
not started
✓
FIT-120
Stud partition L2
2027-08-24
2027-09-10
2027-09-15
2027-10-01
+22d
+21d
not started
✓
FIT-130
Stud partition L3
2027-09-02
2027-09-20
2027-09-23
2027-10-11
+21d
+21d
not started
✓
FIT-140
Stud partition L4
2027-09-10
2027-09-28
2027-10-01
2027-10-19
+21d
+21d
not started
✓
FIT-150
Stud partition L5-L6
2027-09-20
2027-10-14
2027-10-11
2027-11-04
+21d
+21d
not started
✓
FIT-160
Suspended ceilings L1-L3
2027-09-20
2027-10-25
2027-10-11
2027-11-15
+21d
+21d
not started
✓
FIT-210
Plastering L1-L3
2027-10-06
2027-11-03
2027-10-27
2027-11-24
+21d
+21d
not started
✓
✓
FIT-170
Suspended ceilings L4-L6
2027-10-14
2027-11-18
2027-11-04
2027-12-09
+21d
+21d
not started
✓
FIT-180
Ceiling integration MEP
2027-10-25
2027-11-10
2027-11-15
2027-12-01
+21d
+21d
not started
✓
FIT-220
Plastering L4-L6
2027-11-03
2027-12-01
2027-11-24
2027-12-22
+21d
+21d
not started
✓
✓
FIT-240
Painting L4-L6
2027-12-01
2027-12-29
2027-12-22
2028-01-19
+21d
+21d
not started
✓
✓
FIT-260
Floor finishes L4-L6
2027-12-29
2028-01-28
2028-01-19
2028-02-18
+21d
+21d
not started
✓
✓
FIT-310
Reception joinery
2028-01-06
2028-01-27
2028-01-27
2028-02-17
+21d
+21d
not started
✓
✓
FIT-320
Toilet vanity install
2028-01-06
2028-02-01
2028-01-27
2028-02-22
+21d
+21d
not started
✓
✓
FIT-330
Tea-point joinery
2028-01-13
2028-01-31
2028-02-03
2028-02-21
+21d
+21d
not started
✓
✓
FIT-340
Meeting room joinery
2028-01-20
2028-02-15
2028-02-10
2028-03-07
+21d
+21d
not started
✓
✓
FIT-350
Built-in storage and fittings
2028-02-03
2028-02-24
2028-02-24
2028-03-16
+21d
+21d
not started
✓
✓
FIT-360
Final joinery snagging
2028-02-24
2028-03-07
2028-03-16
2028-03-28
+21d
+21d
not started
✓
✓
MS-FIT-END
Fit-out complete
2028-03-07
2028-03-07
2028-03-28
2028-03-28
+21d
+21d
not started
✓
✓
CMS-210
Client walkthrough and snag list
2028-04-18
2028-04-25
2028-05-09
2028-05-16
+21d
+21d
not started
✓
✓
CMS-220
Major snags rectification
2028-04-25
2028-05-16
2028-05-16
2028-06-06
+21d
+21d
not started
✓
✓
CMS-230
Minor snags rectification
2028-05-04
2028-05-22
2028-05-25
2028-06-12
+21d
+21d
not started
✓
✓
CMS-240
Final inspection
2028-05-16
2028-05-22
2028-06-06
2028-06-12
+21d
+21d
not started
✓
✓
CMS-310
Building handover documentation
2028-05-18
2028-05-30
2028-06-08
2028-06-20
+21d
+21d
not started
✓
✓
CMS-320
O&M manuals issued
2028-05-30
2028-06-05
2028-06-20
2028-06-26
+21d
+21d
not started
✓
✓
CMS-330
Soft landings start
2028-06-05
2028-06-08
2028-06-26
2028-06-29
+21d
+21d
not started
✓
✓
Showing the top 50 most-moved critical-path activities of 91 critical and 148 total matched. Selected by absolute start+finish variance, then re-sorted chronologically. Full matched-activity list in the Matched Activities sheet of the Excel appendix.
11
Critical path — supporting views
Structural views behind the Brief-layer critical-path overlay: the update's critical chain rolled up to WBS level, the dependencies between critical clusters, and the update timeline on the project calendar.
Critical path rollup — WBS summary bars
Summary-bar view of the update's critical path — one bar per WBS cluster that contains stored-critical activities. Near-critical clusters (1–20 wd float, the schedule's status-cycle threshold) are shown alongside in amber so the reader can see which clusters are one slip from the critical path.
Critical path sequence — the driving chain in order
The update's driving path to the project endpoint, read in the direction the arrows point, row by row. Each box is a run of consecutive activities on that path sharing a WBS parent (or a single activity on short chains), labelled with how many activities it covers and its date envelope; shading is stage duration. Every activity on the chain is inside exactly one box — nothing is sampled or dropped.
Update critical path timeline (part 1 of 3)
Stored-critical activities on the post-update schedule plotted on the project calendar. Use alongside the schedule-comparison table to see which activities drive the current completion date.
Update critical path timeline (part 2 of 3)
Stored-critical activities on the post-update schedule plotted on the project calendar. Use alongside the schedule-comparison table to see which activities drive the current completion date.
Update critical path timeline (part 3 of 3)
Stored-critical activities on the post-update schedule plotted on the project calendar. Use alongside the schedule-comparison table to see which activities drive the current completion date.
12
Float paths — detail
The full set of near-critical chains behind the Brief-layer float-path callout, with the overlay chart showing when each chain lands on the calendar. The Excel appendix carries the complete per-activity list per path.
Top 5 float paths
#
Float
Activities
Envelope
Driving activity
Branches from
1
-27 wd
65
2026-02-16 → 2028-06-29
PRE-130 — Building control submission
—
2
-7 wd
66 (1 unique)
2026-03-06 → 2028-06-29
PRE-250 — Site security and CCTV
Path 1 at SUB-110
3
0 wd
47 (3 unique)
2026-11-03 → 2028-06-29
SUP-310 — Slab L1 formwork
Path 1 at SUP-410
4
-6 wd
47 (3 unique)
2026-12-01 → 2028-06-29
SUP-210 — Column starter bars L3
Path 1 at SUP-410
5
-14 wd
38 (11 unique)
2027-02-24 → 2028-06-29
SUP-510 — Roof slab formwork
Path 1 at FIT-110
Float-path overlay — when each near-critical chain lands
One bar per top-5 float path showing its divergent window — the activities unique to this path before it merges into a higher-priority chain, with the float window, data date and contractual milestones marked. Reads at a glance: are the alternatives spread across the programme or crowded into one window?
13
Progress curve
Reading this chart. Three cumulative curves over time: the baseline's planned value (dashed grey), the current plan's planned value (solid blue), and the actual earned value on the update (solid red). Gap between the dashed grey and solid blue lines shows re-planning (work pushed into future periods, independent of actual progress). Gap between solid blue and solid red at the data date shows the current execution gap.
Acronyms. PV = Planned Value (share of total scheduled work due by a date). EV = Earned Value (share actually achieved). SV = Schedule Variance = EV − PV, in working-day equivalents. SPI = Schedule Performance Index = EV ÷ PV; < 1.00 ⇒ behind plan. Printed in the chart title at the data date.
Why duration-weighted. Cost-based EVM (AC / CV / CPI) is not computed because P6 exports routinely strip resource and cost tables. Duration-weighting — each activity contributes in proportion to its original working-day duration — is the industry standard fallback per AACE RP 27R-03. Full formula in METHODOLOGY §5d.
Duration-weighted progress S-curve
Baseline PV (dashed grey), current plan PV (solid blue), actual EV (solid red). Vertical dotted line marks the data date where SPI is computed.
9 of 10 due activities completed by data date, measured vs SL-DEMO — no approved baseline embedded in the file, so this is informational and not scored toward the 14-point total
PAM 200.1 companion metrics
Item
Measured
Threshold
Status
Notes
Hit Task Percentage (PAM 200.1 §3.1.2.4 — BEI companion)
—
≥0.95 (informational; PAM publishes no formal threshold)
Not assessed
no activities have baseline finish dates on or before the status date
15
SCL Appendix B compliance
SCL Appendix B compliance: 6 present, 0 partial, 1 not assessed.
App B §1 — Milestone scheduled / forecast / actual dates. 8 milestone(s) tracked with planned, forecast, and actual dates.
App B §2 — Critical activity identification. Critical activities are the schedule's own stored critical flags; driving paths to contractual milestones are traced through the driving relationships in the programme's own dates; near-critical paths use the schedule's own float.
App B §3 — Progress against baseline. 148 activities matched between the two schedules.
App B §4 — Narrative of changes in the period. Changes are summarised by WBS package and accompanied by recommended next actions.
App B §5 — Period delay enumeration with cause. 6 delay event(s) itemised; 4 (67%) carry both quantified impact and assigned entitlement classification. The remainder are topology events (direction-of-travel signals not sized without TIA) or events the rule-based classifier could not determine origin for from the description alone.
App B §6 — Acceleration measures. No duration reductions detected; activities were not shortened between the two schedules. The App B §6 answer for this period is 'no acceleration measures.'
App B §7 — Risk events. Not assessed by this engine. App B §7 requires identification of risks materialised in the period and forward-looking risks affecting the schedule, sourced primarily from the project's risk register and Monte Carlo schedule risk analysis (where applicable). Neither input is available to a schedule-only engine — this analysis is based on schedule files alone. The contractor's own risk register and any SRA outputs should be referenced alongside this report to address App B §7.
16
Delay by work package
Work packages with delay:4Top 5 by critical-path movement shown below; full rollup is in the Excel appendix.
Delay events aggregated by the work breakdown structure node of each affected activity.
Top 5 work packages by critical-path movement (negative = pulled in):
Foundation Piling — +10 working days net · +10 working days on the critical path · 2 events (2 critical)
Excavation — +5 working days net · +5 working days on the critical path · 1 events (1 critical)
Permits & Approvals — +4 working days net · +4 working days on the critical path · 1 events (1 critical)
Plumbing & Fire — +14 working days net · 0 working days on the critical path · 1 events (0 critical)
The full rollup — every WBS node with a recorded event — is in the Excel appendix under the Delay Register sheet (filter by WBS column).
Activities that exist in one schedule but not the other. Added activities represent new scope; removed activities represent scope deletion.
Added activities: 1 (total planned duration 14 working days)
Removed activities: 0
The activity matching process uses four cascading strategies before an activity falls into these pools:
Exact ID
Normalised ID
Name plus WBS path
Name-only fallback
Surviving entries are genuine scope changes, not renumbering or WBS-restructuring artefacts.
Full per-activity lists (every added and removed activity) are in the Excel appendix under the Scope Changes tab.
18
Recommendations
Actions identified:2Findings-driven go-forward actions. Each recommendation traces to a specific finding, warning, or metric in this report.
The largest critical event on this analysis is SUB-210 — Piling rig mobilisation, a Duration change event adding 6 working days in isolation. The recommendations below should be applied to this event as a priority before the lower-impact items.
Concrete next actions derived from this analysis. Every recommendation below references a specific number, finding, or warning elsewhere in the report — nothing speculative.
Industry precedent (AACE RP 29R-03 §4.3; CIOB Guide §5.5) treats this section as a required deliverable element of any forensic report.
Prepare narrative and evidence for the 2 critical events with a material isolated contribution (≥5 working-day movement of the project finish; largest = 6 wd). That column in the delay register carries the per-event figure; for each flagged event the forensic record should document cause, contractual position, and supporting documentation.
Review the 1 added activity event(s) flagged 'Not assessed' in the Entitlement column. The classifier could not determine origin from the description alone; these need to be checked against the variation register and contract to assign an Employer risk / Contractor risk classification.
Full forensic record
Forensic appendix
Full evidence, registers, methodology, standards citations.
19
Scheduling options
Schedule calculated under Retained Logic
Retained Logic preserves the original network sequence through out-of-sequence progress — a partially-complete activity still waits for its predecessors to finish before continuing. This is the conservative, forensic-friendly default.
Total float calculated using finish float
Total float can be computed relative to the earliest start, the latest finish, or the lower of the two — P6 stores the project's choice here for disclosure on any report that quotes float values.
20
Delay and change register
Identified changes:6
The register below lists every identified change between baseline and update. Each row carries an Impact basis tag (matching the chart that follows) so the reader can immediately see whether its delay-days value is a directly-measured figure or a placeholder:
Activity-level (measured) — Duration change and Progress shortfall events. The delay-days value is a directly-measured working-day figure (update duration minus baseline duration for duration changes, or days-behind-current-plan for progress events).
Scope — upper bound — Added scope and Removed scope events. The activity's own planned duration is shown as an upper bound; the real delay contribution depends on whether the activity sits serially on the critical path, which this engine does not verify per event.
Topology (engine-unresolved) — Logic change, Constraint change, and Calendar change events. These carry a 0 delay-days value because the engine cannot size each event's isolated contribution without a calendar-aware CPM pass per event (METHODOLOGY §5a).
Positive delay values indicate delay to the project finish; negative values indicate acceleration. The Isolated contribution (wd) column gives, for each critical event, the working-day movement of the project finish when that event's change alone is reverted out of the update. It is a screening measure for triage, not an entitlement figure: it is subtractive and retrospective, so it is not a time impact analysis, which is additive and prospective (AACE MIP 3.6/3.7; CIOB §5.8.36, §5.8.40). The figures are isolated from one another and must not be summed (METHODOLOGY §5a.5). Events off the critical path show "—"; events whose category is not resolvable by the calendar- and constraint-agnostic trace (constraint / calendar changes) show "see note" — see METHODOLOGY §5a for the limitation. The Entitlement (prelim.) column carries a rule-based first-pass classification per SCL Protocol §10.4 (Employer risk / Contractor risk / Neutral / Concurrent / Not assessed). The first-pass reads activity descriptions for cause-of-delay keywords and falls back to category-default rules where no keyword fires. Verify every classification against the contract, the variation register, NCRs, and documentary evidence before relying on it in any formal correspondence — the final call is a legal / contractual determination this tool does not make.
Composition by category:
Duration change: 3
Progress shortfall: 1
Logic change: 1
Added scope: 1
Register composition
Register split by the three Impact basis buckets defined above — Activity-level (measured), Scope (upper bound), and Topology (0 without CPM). Bar width shows the event count in each bucket; percentages sum to 100 across the register.
Delay events (summary)
Ref
Category
Activity
Delay
Impact basis
Isolated contribution (wd)
Critical
Period
Entitlement (prelim.)
DE-001
Progress shortfall
PRE-130
+4 working days
Activity-level
+4 working days
✓
2026-03-02 → 2026-03-06
Contractor risk
DE-002
Duration change
SUB-110
+5 working days
Activity-level
+5 working days
✓
2026-03-23 → 2026-04-17
Contractor risk
DE-003
Duration change
SUB-210
+6 working days
Activity-level
+6 working days
✓
2026-04-10 → 2026-04-24
Contractor risk
DE-004
Duration change
SUB-240
+4 working days
Activity-level
+4 working days
✓
2026-06-08 → 2026-06-22
Contractor risk
DE-005
Logic change
SUP-330, SUP-440
0 working days
Topology
0 working days
✓
2027-01-04 → 2027-01-14
Neutral
DE-006
Added scope
MEP-355
+14 working days
Scope — upper bound
—
2027-06-21 → 2027-07-09
Not assessed
Delay events (detail)
Ref
Internal id
Description
DE-001
prg:PRE-130
Activity PRE-130 (Building control submission): no recorded finish at the data date (2026-03-06); 4 working day(s) behind the update schedule's own forecast finish of 2026-03-02.
Review note. Activity is 4 working day(s) behind its own current plan at the data date; default Contractor risk. Check the cause-of-delay log and the contemporaneous progress records for documented reasons.
DE-002
dur:SUB-110
Activity SUB-110 (Bulk excavation Zone A): duration increased from 12 to 17 working days (+5).
Review note. Activity duration extended by 5 working day(s) with no external-cause keyword in the description; default Contractor risk. Check NCRs, resource-histogram variance, and subcontractor correspondence for contributory cause.
DE-003
dur:SUB-210
Activity SUB-210 (Piling rig mobilisation): duration increased from 4 to 10 working days (+6).
Review note. Activity duration extended by 6 working day(s) with no external-cause keyword in the description; default Contractor risk. Check NCRs, resource-histogram variance, and subcontractor correspondence for contributory cause.
DE-004
dur:SUB-240
Activity SUB-240 (Pile integrity testing): duration increased from 6 to 10 working days (+4).
Review note. Activity duration extended by 4 working day(s) with no external-cause keyword in the description; default Contractor risk. Check NCRs, resource-histogram variance, and subcontractor correspondence for contributory cause.
DE-005
log:SUP-330->SUP-440:added
Relationship SUP-330 (Slab L1 pour) → SUP-440 (Slab L4 formwork) added (SS with lag +2).
Review note. Logic change — the network re-wiring affects critical-path sequencing. A calendar- and constraint-aware CPM pass on this specific edit is required to quantify its effect on completion. Investigate who initiated the change and whether it was authorised by the contract.
DE-006
add:MEP-355
Activity MEP-355 (Additional fire-water tank install) added — new scope of 14 working day(s). Delay contribution shown is an upper bound; the true impact depends on whether the activity lies serially on the driving path.
Full description for each event. The internal id links events back to the engine output and is useful when reconciling figures against the underlying analysis data.
Gross critical delay contribution by category
Each category's gross critical contribution (activity-level). This double-counts along critical chains and excludes acceleration and float absorption, so it is not the net finish delay. Excludes topology events whose impact is not quantified.
21
Concurrent delay
This section lists time windows where two or more independent critical delay events overlap. The "net impact" column shows the delay days that flow through to the project completion date under the methodology named in the disclosure at the top of the report; the "absorbed" column shows delay days that would otherwise have been counted twice and are removed from the total.
The delay register contains 4 measurable critical events. None met the SCL §10.4 independence test for concurrency — the events are either causally linked in the schedule network (one activity is upstream of the other in either the baseline or the update) or their time windows do not overlap. This is a defensible zero, not an absence of analysis: SCL true concurrency requires two or more independent critical chains contending for the finish during the same period. Where a schedule shows a single dominant delay chain — for example a vendor procurement sequence or a commissioning chain — the events on that chain are causally linked and correctly excluded. Where two or more independent chains exist, this section will populate with the windows during which they overlap. Review the delay register and the schedule logic to confirm the chain structure is expected.
22
DCMA detail — offending activities
The activities and relationships behind each failing DCMA item, most severe first. Tables are capped at 20 rows; the Excel appendix's “DCMA detail” sheet carries the full lists.
§3 Lags — 9 of 155 relationships
Ref
Name
Value
MEP-280 → FIT-160
Insulation and labelling → Suspended ceilings L1-L3
Cladding survey and setting-out → Cladding North elevation
SS lag +5 wd
FIT-110 → FIT-120
Stud partition L1 → Stud partition L2
SS lag +4 wd
FIT-120 → FIT-130
Stud partition L2 → Stud partition L3
SS lag +4 wd
FIT-130 → FIT-140
Stud partition L3 → Stud partition L4
SS lag +4 wd
FIT-140 → FIT-150
Stud partition L4 → Stud partition L5-L6
SS lag +4 wd
SUP-330 → SUP-440
Slab L1 pour → Slab L4 formwork
SS lag +2 wd
§6 High Float — 27 activities with > 44 wd float (showing 20 of 27 — full list in the Excel appendix)
Ref
Name
Value
EXT-110
External drainage
200 wd float
EXT-120
Sub-base preparation
200 wd float
EXT-130
Tarmac surfacing
200 wd float
EXT-140
Line marking and signage
200 wd float
EXT-210
Soft landscape preparation
200 wd float
EXT-220
Planting and turf
200 wd float
EXT-230
Hard landscape features
200 wd float
EXT-310
Boundary fencing
199 wd float
EXT-320
Gates and access controls
199 wd float
MEP-355
Additional fire-water tank install
124 wd float
MEP-320
Riser plumbing
113 wd float
MEP-330
Floor plumbing L1-L3
113 wd float
MEP-340
Floor plumbing L4-L6
113 wd float
MEP-350
Sprinkler mains
113 wd float
MEP-360
Sprinkler floor distribution
113 wd float
CMS-110
Mechanical commissioning
98 wd float
CMS-120
Electrical commissioning
98 wd float
CMS-130
BMS integration and tuning
98 wd float
CMS-140
Fire and life-safety witness tests
98 wd float
CMS-150
Air leakage and BREEAM tests
98 wd float
§7 Negative Float — 80 activities with negative float (showing 20 of 80 — full list in the Excel appendix)
Ref
Name
Value
PRE-130
Building control submission
-27 wd float
FIT-210
Plastering L1-L3
-15 wd float
FIT-220
Plastering L4-L6
-15 wd float
FIT-240
Painting L4-L6
-15 wd float
FIT-260
Floor finishes L4-L6
-15 wd float
FIT-310
Reception joinery
-15 wd float
FIT-320
Toilet vanity install
-15 wd float
FIT-330
Tea-point joinery
-15 wd float
FIT-340
Meeting room joinery
-15 wd float
FIT-350
Built-in storage and fittings
-15 wd float
FIT-360
Final joinery snagging
-15 wd float
MS-FIT-END
Fit-out complete
-15 wd float
CMS-210
Client walkthrough and snag list
-15 wd float
CMS-220
Major snags rectification
-15 wd float
CMS-230
Minor snags rectification
-15 wd float
CMS-240
Final inspection
-15 wd float
CMS-310
Building handover documentation
-15 wd float
CMS-320
O&M manuals issued
-15 wd float
CMS-330
Soft landings start
-15 wd float
MS-PC
Practical Completion
-15 wd float
§9 Invalid Dates — 1 activities with dates inconsistent with data date 2026-03-06
Ref
Name
Value
PRE-130
Building control submission
forecast finish 2026-03-02 before data date
23
Float consumption detail
Float lost by WBS package
WBS
Float lost (typical)
Activities eroding
RC Columns L1-L3
15 wd
9
Curtain Wall
15 wd
8
Partitions & Ceilings
15 wd
8
Finishes & Decoration
15 wd
8
Electrical Rough-In
15 wd
8
Mechanical & HVAC
15 wd
8
Joinery & Fixtures
15 wd
6
Plumbing & Fire
15 wd
6
Slab Pours L1-L3
15 wd
6
Slab Pours L4-L6
15 wd
6
How float consumption is measured
Float consumed is the reduction in CPM-recomputed total float on activities matched between the baseline and this update. 148 of 148 matched float-bearing activities were compared on a like-for-like basis; 0 were excluded because their constraint changed or they moved to a different calendar, which shifts float wholesale and would otherwise read as erosion.
24
Delay timeline
Timeline visualisation of delay events plotted against the project schedule. Events are coloured by category; concurrent-delay windows are shaded.
Delay events and concurrent periods
25
Methodology
This report assesses the uploaded schedule against the published industry standards listed below. Each finding traces to a specific rule in one or more of those standards. The analysis is automated and deterministic — the same schedule file will always produce the same findings.
Scope of this analysis. This report is based solely on the schedule file(s) you uploaded. Determinations that — under AACE RP 29R-03, the SCL Delay & Disruption Protocol, or other cited standards — require evidence outside the schedule file have been flagged as candidates rather than concluded. Specifically, the following determinations and analyses require manual verification by a qualified delay analyst before being relied on for contractual purposes:
Pacing vs concurrency — distinguishing contractor pacing (AACE §4.2.F / SCL §10) from independent concurrent delay requires contemporaneous notice, correspondence, and resource records that are outside the scope of schedule-only analysis.
Constructive acceleration — identifying directed or constructive acceleration (AACE §4.4) requires correspondence and contract notices not available to the engine.
Contractual classification — categorising delay events as excusable, compensable, or non-excusable depends on contract terms outside the schedule file.
Concurrency during the overlap window — the SCL §10.4 test asks whether two delays were both critical during their overlap. The engine evaluates this as the union of the two schedules' critical-path membership, which is a snapshot-level approximation of the window-level test. A precise test would require a CPM walk per overlap interval, which is outside V1 scope. The approximation will under-detect concurrency where an activity was on the critical path only during a sub-window of the overlap and not at either snapshot date.
As-built critical path — the report does not produce a stitched as-built critical path across multiple updates. On comparison reports the per-update critical path is shown for each schedule in the comparison (Driving Path section); on series reports an interim methodology paragraph describes the per-period substitute. A V1.1 release will add a cross-period as-built CP synthesis section to the series report Brief layer.
Date basis. Every start and finish date in this report is each schedule's *current forecast* — the date work is now expected to occur, or its recorded actual date where the work is complete. In Primavera P6 that is the Remaining Early date; in Microsoft Project and Asta Powerproject it is the scheduled Start/Finish. The report does not use a tool's frozen Planned/target dates, which stop updating once an activity is in progress and so understate movement on a progressed schedule. Baseline dates stored inside a file (e.g. a P6 baseline) are read as recorded, and every variance compares the current forecast on each side.
Float and criticality — the source tool's — every total-float and critical-path figure in this report (including the DCMA float checks, float paths, near-critical detection and milestone deliverability) is the value recorded by the scheduling tool that produced the file. ScheduleLens does not overwrite it. Where the source recorded no float and the activity is incomplete, ScheduleLens's own calendar-aware pass supplies one; completed activities are left unfloated rather than given an invented value. That gap-filling pass applies Retained Logic/Progress Override per the file's scheduling options but does not model Start/Finish-No-Later-Than or As-Late-As-Possible constraints, Expected Finish forcing, or an imposed must-finish date. ScheduleLens's own critical-path pass is used for change between two schedules — critical-path churn, bounded what-if, retained-logic versus progress-override, between-snapshot slip — where both sides run through the same engine; those figures are labelled as ScheduleLens's. Where the independent pass disagrees with the file's own critical flags, the disagreement is reported by the critical-path staleness check rather than resolved.
Engine-attributed-vs-observed divergence — the engine-attributed delay figure is an attribution of observed completion movement to specific activity-level events. It can diverge from the observed figure in either direction. Undercount divergence (engine attributes less than observed) typically reflects unquantified topology changes, scope absorption, or parallel-path absorption the activity-level formula cannot capture without a CPM recalculation. Overstate divergence (engine attributes more than observed) typically reflects double-counting along a critical chain, scope-add events whose full duration is being counted, or concurrency absorption gaps. In both directions the observed figure is authoritative for the headline; the engine-attributed figure is a subordinate diagnostic surfacing what specific events contributed.
Where the engine raises a candidate flag for any of these determinations, the relevant section explicitly says so. The engine does produce a rule-based first-pass entitlement classification on each delay-register row (Employer risk, Contractor risk, Neutral, Concurrent, or Not Assessed) — this is a preliminary tagging based on activity-description keywords and category defaults, not a contractual determination. The classification is presented as '(prelim.)' in the column header and every row carries a review-note prompt to verify against the contract, the variation register, NCRs, and documentary evidence before relying on it.
Units. Day figures in this report are calendar days unless they are marked as working days. Two different quantities are being measured and the distinction is deliberate.
Movement between two dates — how far completion, a milestone or the schedule end has moved between submissions — is reported in calendar days. Elapsed time is the same quantity for every activity on a programme, so figures measured this way can be compared with each other, and they do not change when a calendar's holidays are edited. AACE RP 29R-03 directs that as-built comparison be carried out in calendar days for this reason, and cautions that float expressed in workday units differs between activities on different calendars; SCL Protocol §8.8 gives the same caution where multiple work-day calendars are in use.
Schedule properties — float, activity durations, the delay quantum recorded against each event, and the DCMA thresholds — are reported in working days, and are marked as such wherever they appear. These are not spans between two dates and have no calendar-day equivalent: an activity whose duration grows from 10 to 20 working days has no single elapsed-day value, because that depends on where in the calendar the work falls. The DCMA 14-point checks define their thresholds in working days, so restating them would change what is being tested.
A working-day figure is counted on the calendar assigned to the activity it describes, not on the project default — on a programme running five-day and seven-day calendars together, the same elapsed period is a different number of working days for different activities.
Use of AI. The ScheduleLens analysis engine computed every finding, figure, score and chart in this report. At the requester's election, a language model (qwen3-6-27b, via Venice) then wrote the explanatory prose in the sections “Executive Summary”, “What happened · Why · Where to investigate” and “Float-path risk”. It worked only from those computed results. It did not see the schedule file and did no analysis of its own. Where prose and a table or chart differ, the table or chart governs.
Standards referenced
Short name
Full title
Edition
Sections cited
DCMA 14-Point
DCMA EVMS Program Analysis Pamphlet (PAM) — §4 14 Point Schedule Metrics for IMS Analysis
GAO Schedule Assessment Guide — Best Practices for Project Schedules
GAO-16-89G
Best Practice 1, Best Practice 2, Best Practice 3, Best Practice 4, Best Practice 5, Best Practice 6, Best Practice 7, Best Practice 8, Best Practice 9, Best Practice 10
PMBOK
PMI Body of Knowledge — Schedule Management
§2.3
ScheduleLens is not affiliated with, endorsed by, or certified by AACE International, the Project Management Institute, the Defense Contract Management Agency, the Chartered Institute of Building, the Society of Construction Law, or the Government Accountability Office. Citations to these standards in this report are bibliographic, indicating the analytical basis for each check.