ScheduleLens Schedule Health

Project

SL-DEMO

2026-03-09 · sourced from XER

Schedule health

Amber

2 warnings — schedule quality acceptable with minor concerns.

Red flags

0

Warnings

2

Warning-severity findings — review before relying on the dates.

Critical-path activities

69

Remaining activities the source CPM flagged critical. A set, not one chain.

Near-critical activities

25

Within 1–20 working days of total float, one status cycle from critical.

DCMA score

B · 9 of 11 assessed

Checks passed (3 not assessed).

Data date

2026-03-06

3 calendar days ago.

Contract finish

2028-07-03

Practical Completion · 0 wd float.

Programme finish

2028-07-03

Practical Completion · same date as contract finish.

Activities

149

Contents

Schedule Health

  1. — Disclosures
  2. Brief
  3. 01 Executive Summary
  4. 02 Signals
  5. 03 Where to focus first
  6. 04 Key Milestones
  7. 05 What to do next
  8. Narrative
  9. 06 Completion forecast
  10. 07 Float-path risk
  11. 08 Progress curve
  12. 09 Float paths — detail
  13. 10 DCMA 14-Point compliance — full scorecard
  14. 11 Critical path to Practical Completion
  15. 12 Float analysis
  16. 13 What to do next: further questions and recommendations
  17. Appendix
  18. 14 Findings
  19. 15 Critical path activities
  20. 16 Logic quality
  21. 17 Open ends
  22. 18 Schedule metadata
  23. 19 DCMA detail — offending activities
  24. 20 Excel appendix guide
  25. 21 Methodology
  26. 22 Appendix A — Reference Standards

Disclosures

Analytical tool output — not expert determination

This report is automatically generated from the uploaded schedule file(s). It is an analytical aid — not an expert determination, legal advice, or a certified forensic delay analysis.

Float and criticality are the source scheduling tool's own, as recorded in the file. The tool runs its own calendar-aware critical-path pass to fill a gap where the source recorded no float on incomplete work, and to measure change between two schedules. That pass is an analytical recompute, not a substitute for re-scheduling in P6 or MS Project: it does not level resources, force Expected Finish or imposed-finish dates, or work at sub-day precision. It cannot determine contractual excusability.

Figures should be reviewed by a qualified delay analyst before being relied upon in formal contract correspondence or dispute proceedings. Nothing in this report should be construed as a legal opinion or expert witness statement.

Brief

For the project directorSeverity-coded status headlines, top risks, what to act on.

01

Executive Summary

The schedule health assessment returns an Amber rating, indicating acceptable quality with minor concerns and no critical red flags. The primary finding is the presence of 28 activities with float exceeding 44 working days, which suggests the critical path may not accurately reflect the longest duration path. This structural issue, alongside 13 relationships with positive lag, requires review to ensure the reported dates are reliable for decision-making. The reader should examine the float analysis and relationship checks to verify the integrity of the critical path.

02

Signals

Completion forecast Needs your baseline Programme finish: 2028-07-03. → §06
Near-critical paths 8 sub-critical or parallel-critical, within 20 working days of the controlling path. → §07
DCMA 14-Point compliance 9 of 11 assessed — 2 fails, 3 not assessed → §10
03

Where to focus first

Priority packages: 5 Top 5 WBS packages by impact score (8 total buckets carry at least one signal).

The Superstructure and MEP Rough-In packages carry the highest impact scores, driven primarily by a concentration of near-critical activities. These areas warrant immediate review to assess the stability of the current schedule logic.

Priority WBS packages
PackageCriticalWarningAffectedNear-crit.Top issues
Superstructure 0 1 11 9 Activities with float over 44 working days (2 of 28); Near-critical activities (9 of 25)
MEP Rough-In 0 1 13 6 Activities with float over 44 working days (7 of 28); Near-critical activities (6 of 25)
Building Envelope 0 0 8 7 Activity with duration over 44 working days (1 of 1); Near-critical activities (7 of 25)
Pre-Construction 0 0 1 5 Near-critical activities (1 of 25)
Interior Fit-Out 0 1 4 2 Activities with float over 44 working days (2 of 28); Near-critical activities (2 of 25)
04

Key Milestones

Key milestones: 4 Auto-detected from the contractual-milestone dictionary, plus critical-path finish milestones as a fallback for custom names.

Contract finish (your answer): 2028-07-03, Practical Completion · 0 wd float.

The contractual and progress dates the project is managed against — Practical Completion, sectional handovers, commissioning — auto-detected and ranked critical-first, lowest float first.

Key milestones — forecast dates and progress
MilestoneForecast startForecast finishActual startProgressTotal floatOn critical path
Substructure complete 2026-10-26 2026-10-26 — 0% 0 wd Yes
Envelope watertight 2027-08-24 2027-08-24 — 0% 0 wd Yes
Fit-out complete 2028-04-21 2028-04-21 — 0% 0 wd Yes
Practical Completion 2028-07-03 2028-07-03 — 0% 0 wd Yes
05

What to do next

2 questions for the programme's author, none critical. In §13: 2 to clarify.

Narrative

For the planner or delay analystSupporting analysis, schedule comparison, driving-path detail.

06

Completion forecast

Completion forecast: Needs your baseline Programme finish: 2028-07-03.

A forecast needs your baseline programme. Earned Schedule (PMI Standard for EVM, 2019) measures progress against the plan you agreed; run a comparison with your baseline, or track this project, to see it. The programme's own finish is 2028-07-03.

07

Float-path risk

Near-critical paths: 8 sub-critical or parallel-critical, within 20 working days of the controlling path.

Where else forward risk sits: alternative chains to the project end within 20 working days of the critical path. See Methodology (§21).

8 sub-critical paths within 20 working days of critical — a delay on any of them could shift the controlling path. Rank 1 in the table below is the primary critical path for reference.

Top 3 float paths
#FloatActivitiesEnvelopeDriving activityBranches from
1 0 wd 69 2026-03-02 → 2028-07-03 PRE-140 — Building control approval —
2 7 wd 69 (1 unique) 2026-03-06 → 2028-07-03 PRE-250 — Site security and CCTV Path 1 at SUB-110
3 7 wd 35 (8 unique) 2026-10-26 → 2028-07-03 MEP-110 — Main intake and switchgear Path 1 at FIT-110

Top 3 of 9 paths shown (the primary driving path plus 8 near-critical) — the full 5-path table and the float-path overlay chart are in Float paths — detail; every path is in the Excel appendix.

08

Progress curve

Reading this chart. Two cumulative curves over time: where the schedule should be (Planned Value, solid navy) and where it actually is (Earned Value, solid teal). The vertical dotted line is the data date; the gap between the two curves at that line is the current schedule performance.

Acronyms.

Why duration-weighted. P6 / MS Project exports routinely strip resource and cost data, so a cost-weighted EV is not always available. Duration-weighting is used instead: each activity contributes in proportion to its original working-day duration rather than its budget. Full formula and caveats: see Methodology (§21).

Duration-weighted progress S-curve

image/svg+xml schedule-analyser Jan 26 May 26 Sep 26 Jan 27 May 27 Sep 27 Jan 28 May 28 Progress ratio 0.92 at the data date · EV 5.4% · PV 5.9% · SV -0.5pp 0 20 40 60 80 100 Cumulative % complete (duration-weighted) Data date 6 Mar 2026 Planned band (early to late dates) Planned value (current plan) Earned value (actual progress)
Current plan PV (solid navy) vs actual EV (solid teal). Vertical dotted line marks the data date where the progress ratio is read.
09

Float paths — detail

The full set of near-critical chains behind the Brief-layer float-path callout, with the overlay chart showing when each chain lands on the calendar. The Excel appendix carries the complete per-activity list per path.

Top 5 float paths
#FloatActivitiesEnvelopeDriving activityBranches from
1 0 wd 69 2026-03-02 → 2028-07-03 PRE-140 — Building control approval —
2 7 wd 69 (1 unique) 2026-03-06 → 2028-07-03 PRE-250 — Site security and CCTV Path 1 at SUB-110
3 7 wd 35 (8 unique) 2026-10-26 → 2028-07-03 MEP-110 — Main intake and switchgear Path 1 at FIT-110
4 8 wd 47 (3 unique) 2026-12-03 → 2028-07-03 SUP-210 — Column starter bars L3 Path 1 at SUP-410
5 14 wd 47 (3 unique) 2026-11-13 → 2028-07-03 SUP-310 — Slab L1 formwork Path 1 at SUP-410

Float-path overlay — when each near-critical chain lands

image/svg+xml schedule-analyser Jul 26 Jan 27 Jul 27 Jan 28 Jul 28 Jan 29 Path 1 (critical) · 0 wd · 69 act. Path 2 · 7 wd · 1 act. Path 3 · 7 wd · 8 act. Path 4 · 8 wd · 3 act. Path 5 · 14 wd · 3 act. PRE-140 — Building control approval PRE-250 — Site security and CCTV MEP-110 — Main intake and switchgear SUP-210 — Column starter bars L3 SUP-310 — Slab L1 formwork M1 M2 M3 M4 Critical path (Path 1) Alternative chain (divergent window) Float window (total float, approx. calendar) Data date M1 — Substructure complete M2 — Envelope watertight M3 — Fit-out complete M4 — Practical Completion
One bar per top-5 float path showing its divergent window — the activities unique to this path before it merges into a higher-priority chain, with the float window, data date and contractual milestones marked. Reads at a glance: are the alternatives spread across the programme or crowded into one window?
10

DCMA 14-Point compliance — full scorecard

DCMA 14-Point compliance: 9 of 11 assessed — 2 fails, 3 not assessed

DCMA 14-Point Assessment: 9 pass, 2 fail, 3 not assessed.

DCMA 14-Point items
ItemMeasuredThresholdStatusNotes
§1 Logic 0.8% ≤5% of incomplete activities Pass 1 of 131 activities assessed
§2 Leads 0 0 (none allowed) Pass 0 negative lag(s)
§3 Lags 7.8% ≤5% of relationships Fail 12 of 154 relationships
§4 Relationship Types 90.9% ≥90% Finish-Start Pass 140 of 154 are Finish-Start
§5 Hard Constraints 0.0% ≤5% of incomplete activities Pass 0 hard constraint(s)
§6 High Float 21.4% ≤5% of incomplete activities Fail 28 activities with > 44 wd float
§7 Negative Float 0 0 (none allowed) Pass 0 activities with negative float
§8 High Duration 0.8% ≤5% of incomplete activities Pass 1 activity longer than 44 wd
§9 Invalid Dates 0 0 (none allowed) Pass 0 activities with dates inconsistent with data date 2026-03-06
§10 Resources — Not assessed PAM 200.1 §4.10: the IMS DID does not require resource loading, so DCMA publishes no canonical threshold for this item
§11 Missed Tasks — ≤5% of activities with baseline finish on or before status date Not assessed schedule has no baseline finish dates
§12 Critical Path Test Pass Pass / Fail Pass critical activities identified — note this item tests for their presence, not for an unbroken chain to the project finish; see the Open ends section
§13 Critical Path Length Index 1.00 ≥0.95 Pass CP length 593 wd to Practical Completion, finish float 0 wd
§14 Baseline Execution Index — ≥0.95 Not assessed schedule has no baseline finish dates
PAM 200.1 companion metrics
ItemMeasuredThresholdStatusNotes
Cumulative Hit Task Percentage (PAM 200.1 §3.1.2.4 — BEI companion) — ≥0.95 (informational; PAM publishes no formal threshold) Not assessed no activities have baseline finish dates on or before the status date
11

Critical path to Practical Completion

Programme finish target date: 2028-07-03 — zero days of slack A slip on an activity below pushes the programme finish date if it sits on a chain that reaches the finish and is not recovered on that same chain. 850 calendar days from the data date.

What controls the project finish date: every activity the source scheduling tool flagged as critical, which on a large programme is many chains.

The 69 activities in this set are flagged as critical by the source scheduling tool's own calendar-aware CPM.

This is the critical set, not a single chain. On a large programme it holds many chains running in parallel — the Gantt below orders them by date, not by logic, so two adjacent rows are usually not linked to each other. A slip on one of them delays the project finish only if it sits on a chain that reaches the finish, and only if it is not offset by acceleration on that same chain. The Critical path sequence chart below traces the single controlling chain end to end, in logic order.

This is the remaining critical set: activities already complete are excluded, because finished work no longer drives the finish date. The cover tile counts the same set. Completed activities that were flagged critical are in the Excel appendix's Critical Path tab.

The critical-path finding in the analysis section reports any material disagreement between this stored set and ScheduleLens' own recalculation.

Critical path rollup — WBS summary bars

image/svg+xml schedule-analyser May 26 Sep 26 Jan 27 May 27 Sep 27 Jan 28 Showing 15 of 28 WBS clusters. Permits & Approvals Excavation Foundation Piling Pile Caps & Ground Beams Basement Slab Substructure RC Columns L1-L3 Slab Pours L1-L3 Slab Pours L4-L6 Roof Slab Curtain Wall Windows & Doors Building Envelope Partitions & Ceilings Finishes & Decoration 1 act. 1 act. 5 act. 4 act. 4 act. 1 act. 6 act. 3 act. 6 act. 3 act. 4 act. 3 act. 1 act. 8 act. 4 act. Critical (flagged in the source programme)
One bar per WBS cluster that contains at least one critical or near-critical activity. Bar span is the cluster's envelope (earliest start to latest finish); the count at the right is the number of stored-critical activities in the cluster.

Critical path sequence — the driving chain in order

image/svg+xml schedule-analyser Permits & Approvals to Excavation 2 act. 02 Mar 26 – 16 Apr 26 Foundation Piling 5 act. 17 Apr 26 – 16 Jul 26 Pile Caps & Ground Beams 4 act. 17 Jul 26 – 07 Sep 26 Basement Slab 4 act. 08 Sep 26 – 23 Oct 26 Substructure 1 act. 26 Oct 26 RC Columns L1-L3 6 act. 26 Oct 26 – 02 Dec 26 Slab Pours L1-L3 3 act. 03 Dec 26 – 06 Jan 27 Slab Pours L4-L6 6 act. 07 Jan 27 – 09 Mar 27 Roof Slab 3 act. 10 Mar 27 – 14 Apr 27 Curtain Wall 4 act. 15 Apr 27 – 08 Jul 27 Windows & Doors 3 act. 09 Jul 27 – 23 Aug 27 Building Envelope 1 act. 24 Aug 27 Partitions & Ceilings 8 act. 24 Aug 27 – 24 Nov 27 Finishes & Decoration 4 act. 01 Nov 27 – 22 Feb 28 Joinery & Fixtures 6 act. 01 Feb 28 – 20 Apr 28 Interior Fit-Out 1 act. 21 Apr 28 Snagging & Punchlist 4 act. 21 Apr 28 – 09 Jun 28 Practical Completion 4 act. 12 Jun 28 – 03 Jul 28 69 activities to Practical Completion. Follow the arrows: each row reads in the direction the arrows point, then drops to the row below. Box = consecutive activities on the driving path sharing a WBS parent. Shade: darker = longer stage. 1 box span more than one WBS parent (named first to last) so the whole chain fits; no activity is omitted.
The driving path to the project endpoint, read in the direction the arrows point, row by row. Each box is a run of consecutive activities on that path sharing a WBS parent (or a single activity on short chains), labelled with how many activities it covers and its date envelope; shading is stage duration. Every activity on the chain is inside exactly one box — nothing is sampled or dropped. This is the same path 1 the float-path table ranks; the critical path rollup above shows the same work against the calendar.

Critical path — activities flagged critical in the source programme

image/svg+xml schedule-analyser Jul 26 Jan 27 Jul 27 Jan 28 Jul 28 PRE-140 Building control approval SUB-110 Bulk excavation Zone A SUB-210 Piling rig mobilisation SUB-220 CFA piling Zone A SUB-230 CFA piling Zone B SUB-240 Pile integrity testing SUB-250 Pile trimming SUB-310 Pile cap excavation SUB-320 Pile cap reinforcement SUB-330 Pile cap concrete pour SUB-340 Ground beam install SUB-410 Basement slab formwork SUB-420 Basement slab reinforcement SUB-430 Basement slab waterproofing SUB-440 Basement slab pour MS-SUB-END Substructure complete SUP-110 Column starter bars L1 SUP-120 Column formwork L1 SUP-130 Column pour L1 SUP-140 Column starter bars L2 … 29 more not shown FIT-180 Ceiling integration MEP FIT-210 Plastering L1-L3 FIT-220 Plastering L4-L6 FIT-240 Painting L4-L6 FIT-260 Floor finishes L4-L6 FIT-310 Reception joinery FIT-320 Toilet vanity install FIT-330 Tea-point joinery FIT-340 Meeting room joinery FIT-350 Built-in storage and fittings FIT-360 Final joinery snagging CMS-210 Client walkthrough and snag list MS-FIT-END Fit-out complete CMS-220 Major snags rectification CMS-230 Minor snags rectification CMS-240 Final inspection CMS-310 Building handover documentation CMS-320 O&M manuals issued CMS-330 Soft landings start MS-PC Practical Completion
Activities flagged critical by the source scheduling tool, plotted on the project calendar. Bars span the current dates (actual, else forecast). Showing 40 of 69 critical activities; the full list is in the Excel workbook.
12

Float analysis

Float analysis measures how much delay each activity can absorb before it pushes the project finish. Activities with zero or near-zero float drive the completion date.

Float distribution

image/svg+xml schedule-analyser negative 0 1-10 11-44 >44 Total float (working days) 0 8 16 24 32 40 48 56 64 72 Activities 69 10 28 31
Distribution of total float across incomplete activities. Very high float (DCMA §6: over 44 working days) may result from missing predecessors or successors; DCMA §7 treats negative float as delaying completion of one or more milestones.

Chart colour key:

Note: the cover-page Near-critical activities headline counts activities within the schedule's status cycle rather than the strict 1–10 wd band, so it can include activities that fall in the amber and navy regions of the chart. See Methodology (§21).

Float distribution (counts)
BucketActivities
negative 0
0 69
1-10 10
11-44 28
>44 31
13

What to do next: further questions and recommendations

Questions to clarify

Forensic appendix

Full forensic recordFull evidence, registers, methodology, standards citations.

14

Findings

Findings: 13

Each finding below traces to a specific rule in the cited reference standard.

Severity reflects how far the measured value departs from the published target — critical findings indicate the schedule output itself may be unreliable.

Full citations for each abbreviated standard are listed in Appendix A — Reference Standards.

All findings by severity
SeverityCheckTitleAffectedReference
warning Float analysis 28 activities with float over 44 working days SUB-120, SUB-130, SUB-140, SUP-610, SUP-620 (full list in Excel appendix) DCMA §6 · PMI §3.4.7 · GAO Best Practice 7
warning Relationships 13 relationships with positive lag PRE-110 → PRE-210, SUB-110 → SUB-120, ENV-210 → ENV-220, FIT-110 → FIT-120, FIT-120 → FIT-130 (full list in Excel appendix) DCMA §2/§3/§4 · AACE §4.3.D.3 · PMI §3.2.1.3 · §3.4.9 · §3.4.10 · CIOB §4.25, §4.26
info Calendars 1 calendar in use CIOB §4.13.18
info Constraints 2 constrained activities DCMA §5 · AACE §2 · SCL §1 · PMI §3.4.6 · CIOB §4.27
info Critical path CPLI = 1.00 DCMA §13
info Durations 1 activity with duration over 44 working days ENV-120 DCMA §8 · GAO Best Practice 4
info Float analysis Float distribution PMI §3.4.2 · GAO Best Practice 7
info Float analysis 25 near-critical activities PRE-250, SUP-310, SUP-320, SUP-330, SUP-210 (full list in Excel appendix) AACE §4.3.B.2 · GAO Best Practice 6
info Redundant logic 5 potentially redundant relationships MEP-280 → CMS-110, MS-START → PRE-310, SUB-220 → SUB-250, SUP-110 → SUP-130, MEP-120 → MEP-140 GAO Best Practice 2
info Open ends 1 activity with no predecessor EXT-310 DCMA §1 · AACE §2 · PMI §3.4.7 · CIOB §4.23.1
info Relationships Relationship type distribution DCMA §2/§3/§4 · AACE §4.3.D.3 · PMI §3.2.1.3 · §3.4.9 · §3.4.10 · CIOB §4.25, §4.26
info Scheduling options Schedule calculated under Retained Logic AACE §2.1.B.11, §4.3.D.5 · CIOB §4.30.7.39
info Scheduling options Total float calculated using finish float AACE §4.3.D.5 · CIOB §4.30.7.41
15

Critical path activities

The 69 incomplete activities the source scheduling tool flags as critical, ordered by start date. The Critical path section in the Narrative plots them.

Activities on the critical path
IDNameWBSDuration (wd)Remaining (wd)Float (wd)Forecast startForecast finish
PRE-140 Building control approval Permits & Approvals 15 11 0 2026-03-02 2026-03-20
SUB-110 Bulk excavation Zone A Excavation 17 17 0 2026-03-23 2026-04-16
SUB-210 Piling rig mobilisation Foundation Piling 10 10 0 2026-04-17 2026-04-30
SUB-220 CFA piling Zone A Foundation Piling 18 18 0 2026-05-01 2026-05-27
SUB-230 CFA piling Zone B Foundation Piling 18 18 0 2026-05-28 2026-06-22
SUB-240 Pile integrity testing Foundation Piling 10 10 0 2026-06-23 2026-07-06
SUB-250 Pile trimming Foundation Piling 8 8 0 2026-07-07 2026-07-16
SUB-310 Pile cap excavation Pile Caps & Ground Beams 8 8 0 2026-07-17 2026-07-28
SUB-320 Pile cap reinforcement Pile Caps & Ground Beams 10 10 0 2026-07-29 2026-08-11
SUB-330 Pile cap concrete pour Pile Caps & Ground Beams 6 6 0 2026-08-12 2026-08-19
SUB-340 Ground beam install Pile Caps & Ground Beams 12 12 0 2026-08-20 2026-09-07
SUB-410 Basement slab formwork Basement Slab 8 8 0 2026-09-08 2026-09-17
SUB-420 Basement slab reinforcement Basement Slab 12 12 0 2026-09-18 2026-10-05
SUB-430 Basement slab waterproofing Basement Slab 6 6 0 2026-10-06 2026-10-13
SUB-440 Basement slab pour Basement Slab 8 8 0 2026-10-14 2026-10-23
MS-SUB-END Substructure complete Substructure 0 0 0 2026-10-26 2026-10-26
SUP-110 Column starter bars L1 RC Columns L1-L3 4 4 0 2026-10-26 2026-10-29
SUP-120 Column formwork L1 RC Columns L1-L3 6 6 0 2026-10-30 2026-11-06
SUP-130 Column pour L1 RC Columns L1-L3 4 4 0 2026-11-09 2026-11-12
SUP-140 Column starter bars L2 RC Columns L1-L3 4 4 0 2026-11-13 2026-11-18
SUP-150 Column formwork L2 RC Columns L1-L3 6 6 0 2026-11-19 2026-11-26
SUP-160 Column pour L2 RC Columns L1-L3 4 4 0 2026-11-27 2026-12-02
SUP-340 Slab L2 formwork Slab Pours L1-L3 8 8 0 2026-12-03 2026-12-14
SUP-350 Slab L2 reinforcement Slab Pours L1-L3 8 8 0 2026-12-15 2026-12-24
SUP-360 Slab L2 pour Slab Pours L1-L3 6 6 0 2026-12-29 2027-01-06
SUP-410 Slab L3 formwork Slab Pours L4-L6 8 8 0 2027-01-07 2027-01-18
SUP-420 Slab L3 reinforcement Slab Pours L4-L6 8 8 0 2027-01-19 2027-01-28
SUP-430 Slab L3 pour Slab Pours L4-L6 6 6 0 2027-01-29 2027-02-05
SUP-440 Slab L4 formwork Slab Pours L4-L6 8 8 0 2027-02-08 2027-02-17
SUP-450 Slab L4 reinforcement Slab Pours L4-L6 8 8 0 2027-02-18 2027-03-01
SUP-460 Slab L4 pour Slab Pours L4-L6 6 6 0 2027-03-02 2027-03-09
SUP-510 Roof slab formwork Roof Slab 10 10 0 2027-03-10 2027-03-23
SUP-520 Roof slab reinforcement Roof Slab 8 8 0 2027-03-24 2027-04-06
SUP-530 Roof slab pour Roof Slab 6 6 0 2027-04-07 2027-04-14
ENV-140 Curtain wall install North elevation Curtain Wall 15 15 0 2027-04-15 2027-05-06
ENV-150 Curtain wall install East elevation Curtain Wall 15 15 0 2027-05-07 2027-05-27
ENV-160 Curtain wall install South elevation Curtain Wall 15 15 0 2027-05-28 2027-06-17
ENV-170 Curtain wall install West elevation Curtain Wall 15 15 0 2027-06-18 2027-07-08
ENV-320 Window install upper floors Windows & Doors 12 12 0 2027-07-09 2027-07-26
ENV-330 Window install lower floors Windows & Doors 12 12 0 2027-07-27 2027-08-11
ENV-340 Glazing and seals Windows & Doors 8 8 0 2027-08-12 2027-08-23
FIT-110 Stud partition L1 Partitions & Ceilings 12 12 0 2027-08-24 2027-09-09
MS-ENV-END Envelope watertight Building Envelope 0 0 0 2027-08-24 2027-08-24
FIT-120 Stud partition L2 Partitions & Ceilings 12 12 0 2027-08-31 2027-09-15
FIT-130 Stud partition L3 Partitions & Ceilings 12 12 0 2027-09-06 2027-09-21
FIT-140 Stud partition L4 Partitions & Ceilings 12 12 0 2027-09-10 2027-09-27
FIT-150 Stud partition L5-L6 Partitions & Ceilings 18 18 0 2027-09-16 2027-10-11
FIT-160 Suspended ceilings L1-L3 Partitions & Ceilings 25 25 0 2027-09-16 2027-10-20
FIT-170 Suspended ceilings L4-L6 Partitions & Ceilings 25 25 0 2027-10-21 2027-11-24
FIT-180 Ceiling integration MEP Partitions & Ceilings 12 12 0 2027-11-01 2027-11-16
FIT-210 Plastering L1-L3 Finishes & Decoration 20 20 0 2027-11-01 2027-11-26
FIT-220 Plastering L4-L6 Finishes & Decoration 20 20 0 2027-11-29 2027-12-24
FIT-240 Painting L4-L6 Finishes & Decoration 18 18 0 2027-12-29 2028-01-21
FIT-260 Floor finishes L4-L6 Finishes & Decoration 22 22 0 2028-01-24 2028-02-22
FIT-310 Reception joinery Joinery & Fixtures 15 15 0 2028-02-01 2028-02-21
FIT-320 Toilet vanity install Joinery & Fixtures 18 18 0 2028-02-01 2028-02-24
FIT-330 Tea-point joinery Joinery & Fixtures 12 12 0 2028-02-08 2028-02-23
FIT-340 Meeting room joinery Joinery & Fixtures 18 18 0 2028-02-24 2028-03-20
FIT-350 Built-in storage and fittings Joinery & Fixtures 15 15 0 2028-03-21 2028-04-10
FIT-360 Final joinery snagging Joinery & Fixtures 8 8 0 2028-04-11 2028-04-20
CMS-210 Client walkthrough and snag list Snagging & Punchlist 5 5 0 2028-04-21 2028-04-27
MS-FIT-END Fit-out complete Interior Fit-Out 0 0 0 2028-04-21 2028-04-21
CMS-220 Major snags rectification Snagging & Punchlist 15 15 0 2028-04-28 2028-05-18
CMS-230 Minor snags rectification Snagging & Punchlist 12 12 0 2028-05-19 2028-06-05
CMS-240 Final inspection Snagging & Punchlist 4 4 0 2028-06-06 2028-06-09
CMS-310 Building handover documentation Practical Completion 8 8 0 2028-06-12 2028-06-21
CMS-320 O&M manuals issued Practical Completion 4 4 0 2028-06-22 2028-06-27
CMS-330 Soft landings start Practical Completion 3 3 0 2028-06-28 2028-06-30
MS-PC Practical Completion Practical Completion 0 0 0 2028-07-03 2028-07-03
16

Logic quality

Logic quality checks assess whether the network is fully driven by sequential dependencies. Gaps, excessive non-FS links, and dangling chains all undermine the critical path calculation.

Relationship type distribution
TypeCount
FS 166
SS 14
FF 0
SF 0
Total 180
FS ratio 92.2%
Open ends
FindingCount
1 activity with no predecessor 1
Other logic-quality findings
CheckCount
Redundant relationships 5
17

Open ends

Activities with missing logic — either no predecessor (nothing must happen before them) or no successor (nothing depends on their completion).

DCMA 14-Point §1 expects fewer than 5% of incomplete activities to have open logic.

Review each row and confirm with the planner whether the logic gap is intentional.

Activities with open logic
IDNameWBSIssueDuration (wd)Float (wd)
EXT-310 Boundary fencing Boundary Treatments No predecessor 12 122
18

Schedule metadata

Source and calculation
FieldValue
Source format xer
Data date 2026-03-06
Project start 2026-01-05
Project finish 2028-07-03
Activities 149
Relationships 180
Calendars 1

Scheduling options read from the source file. These govern how the source scheduling tool calculated float and the critical path.

Two options in particular (Progress Override and 'Make open-ended activities critical') can change the reported critical path materially without changing a single activity or relationship.

Any setting that warrants a warning is listed separately in the Findings table above.

Scheduling options
OptionValue
Retained Logic Yes (ON)
Progress Override No (OFF)
Make open-ended activities critical No (recommended)
Float type Finish Float
External-project dependency handling Apply external dates to both start and finish
Use Expected Finish dates Yes
Lag from predecessor early start Yes
Calendar used for relationship lag Predecessor calendar
Source file
FieldValue
P6 version 19.12
Export date 2026-03-06
19

DCMA detail — offending activities

The activities and relationships behind each failing DCMA item, most severe first. Tables are capped at 20 rows; the Excel appendix's “DCMA detail” sheet carries the full lists.

§3 Lags — 12 of 154 relationships
RefNameValue
MEP-280 → FIT-160 Insulation and labelling → Suspended ceilings L1-L3 FS lag +15 wd
CMS-110 → CMS-120 Mechanical commissioning → Electrical commissioning SS lag +8 wd
FIT-170 → FIT-180 Suspended ceilings L4-L6 → Ceiling integration MEP SS lag +7 wd
FIT-260 → FIT-310 Floor finishes L4-L6 → Reception joinery SS lag +6 wd
SUB-110 → SUB-120 Bulk excavation Zone A → Bulk excavation Zone B SS lag +5 wd
ENV-210 → ENV-220 Cladding survey and setting-out → Cladding North elevation SS lag +5 wd
FIT-320 → FIT-330 Toilet vanity install → Tea-point joinery SS lag +5 wd
FIT-110 → FIT-120 Stud partition L1 → Stud partition L2 SS lag +4 wd
FIT-120 → FIT-130 Stud partition L2 → Stud partition L3 SS lag +4 wd
FIT-130 → FIT-140 Stud partition L3 → Stud partition L4 SS lag +4 wd
FIT-140 → FIT-150 Stud partition L4 → Stud partition L5-L6 SS lag +4 wd
SUP-330 → SUP-440 Slab L1 pour → Slab L4 formwork SS lag +2 wd
§6 High Float — 28 activities with > 44 wd float (showing 20 of 28 — full list in the Excel appendix)
RefNameValue
EXT-110 External drainage 123 wd float
EXT-120 Sub-base preparation 123 wd float
EXT-130 Tarmac surfacing 123 wd float
EXT-140 Line marking and signage 123 wd float
EXT-210 Soft landscape preparation 123 wd float
EXT-220 Planting and turf 123 wd float
EXT-230 Hard landscape features 123 wd float
EXT-310 Boundary fencing 122 wd float
EXT-320 Gates and access controls 122 wd float
MEP-355 Additional fire-water tank install 120 wd float
MEP-320 Riser plumbing 109 wd float
MEP-330 Floor plumbing L1-L3 109 wd float
MEP-340 Floor plumbing L4-L6 109 wd float
MEP-350 Sprinkler mains 109 wd float
MEP-360 Sprinkler floor distribution 109 wd float
SUP-610 Roof waterproofing membrane 78 wd float
SUP-620 Roof finishes and parapet 78 wd float
MEP-110 Main intake and switchgear 71 wd float
FIT-230 Painting L1-L3 62 wd float
FIT-250 Floor finishes L1-L3 62 wd float
20

Excel appendix guide

The accompanying .xlsx workbook is the audit companion to this PDF. Wherever the PDF says full list in Excel appendix, the matching tab below carries the unabridged data.

The workbook is laid out in two tiers. The first tier (presentation tabs) gives audit-ready tables of milestones, the critical path, ranked float paths, and the full activity register. The second tier (findings-register tabs) drills into each individual finding with affected activities — one tab per finding.

Tier 1 — presentation tabs
TabContents
Summary Schedule metadata (project dates, activity count) plus every finding with severity, count, and reference. The row to start at when triaging the report.
Key Milestones The full set of detected key milestones with the detection rationale spelled out (contractual keyword, user-supplied keyword, or critical-path WBS-tail fallback). The PDF body is capped at 15; this tab is uncapped.
Critical Path Every activity flagged critical by the source scheduling tool, complete and incomplete. The PDF Critical-path section filters to incomplete-only for clarity; this tab is the unfiltered companion.
Float Paths Every ranked near-critical chain — the full list behind the PDF Float-path risk section's top-5 table. Includes the activity sequence comma-separated for search.
Activities Every activity in the schedule with predecessors and successors inline. The audit substrate — whatever the PDF Findings table references, look up the activity row here to see its surrounding logic.
DCMA detail The full offender lists behind each failing DCMA item — one block per check, most severe first. The PDF's DCMA detail appendix caps at 20 rows per check; this tab is uncapped. Present only when at least one item fails.
Tier 2 — findings-register tabs
TabContents
Float over threshold Activities with total float above DCMA §6's 44-day threshold, which may result from missing predecessors or successors.
Lags Every relationship with a positive lag, with both activities named.
Long-duration activities Activities with planned duration above DCMA §8's 44-day threshold — candidates to break down further.
Near-critical activities Activities within the schedule's status-cycle float band.
Open ends - no predecessor Incomplete activities with no predecessor — they will start on the project start date regardless of true sequencing.
Redundant relationships Finish-to-Start relationships another path already drives, with both activities named.

These are the register tabs this analysis produced. The list is derived from the findings themselves, so it matches the workbook exactly rather than describing every tab the tool can emit.

21

Methodology

This report assesses the uploaded schedule against the published industry standards listed below. Each finding traces to a specific rule in one or more of those standards. The analysis is automated and deterministic — the same schedule file will always produce the same findings.

Scope of this analysis. This report is based solely on the schedule file you uploaded. Two conventions govern how its figures were derived, and both matter when reconciling them against the source tool:

Units. Day figures in this report are calendar days unless they are marked as working days. Two different quantities are being measured and the distinction is deliberate.

Movement between two dates — how far completion, a milestone or the schedule end has moved between submissions — is reported in calendar days. Elapsed time is the same quantity for every activity on a programme, so figures measured this way can be compared with each other, and they do not change when a calendar's holidays are edited. AACE RP 29R-03 directs that as-built comparison be carried out in calendar days for this reason, and cautions that float expressed in workday units differs between activities on different calendars; SCL Protocol §8.8 gives the same caution where multiple work-day calendars are in use.

Schedule properties — float, activity durations, the delay quantum recorded against each event, and the DCMA thresholds — are reported in working days, and are marked as such wherever they appear. These are not spans between two dates and have no calendar-day equivalent: an activity whose duration grows from 10 to 20 working days has no single elapsed-day value, because that depends on where in the calendar the work falls. The DCMA 14-point checks define their thresholds in working days, so restating them would change what is being tested.

A working-day figure is counted on the calendar assigned to the activity it describes, not on the project default — on a programme running five-day and seven-day calendars together, the same elapsed period is a different number of working days for different activities.

Near-critical threshold. Float paths and the near-critical count use a threshold set by the schedule's status cycle, not its length: the question is whether an activity could become controlling, with a small slip, before the next status update. The default is 20 working days, a monthly cycle; it can be set for each project at upload. No published standard prescribes a value. The float distribution chart keeps the DCMA bands (1–10, 11–44 and over 44 working days) so its shape compares across reports, which is why the near-critical count can include activities in the 11–44 band.

Duration-weighted progress. Exported schedules rarely carry cost or resource loading, so the progress curve weights each activity by its original duration. Planned value (PV) at a date is the share of that weighted work the schedule's own planned dates put before it. Earned value (EV) is each activity's original duration multiplied by its percent complete, summed, and divided by the sum of original durations. Summary, level-of-effort and milestone activities are excluded. The progress ratio (EV ÷ PV) is measured against the file's planned dates, not an approved baseline, so it is not the earned-value SPI.

Use of AI. The ScheduleLens analysis engine computed every finding, figure, score and chart in this report. At the requester's election, a language model (qwen3-6-27b, via Venice) then wrote the explanatory prose in the sections “Executive Summary” and “Where to focus first”. It worked only from those computed results. It did not see the schedule file and did no analysis of its own. Where prose and a table or chart differ, the table or chart governs.

Standards referenced
Short nameFull titleEditionSections cited
DCMA 14-Point DCMA EVMS Program Analysis Pamphlet (PAM) — §4 14 Point Schedule Metrics for IMS Analysis DCMA-EA PAM 200.1, October 2012 §1, §2, §3, §4, §5, §6, §7, §8, §9, §10, §11, §12, §13, §14
SCL Protocol SCL Delay & Disruption Protocol, 2nd Edition 2nd Edition (2017) §1, §8.8
AACE RP 29R-03 AACE Recommended Practice 29R-03 — Forensic Schedule Analysis §2, §4.3.D.3, §4.3.D.5, §2.1.B.11, §4.3.B.2
PMI Practice Standard PMI Practice Standard for Scheduling 2nd Edition (2011) §3.2.1.3, §3.4.2, §3.4.6, §3.4.7
CIOB Guide CIOB Guide to Good Practice in the Management of Time 2nd Edition §4.23.1, §4.25, §4.26, §4.27, §4.30.7.39, §4.30.7.41, §4.13.18
GAO Schedule Assessment Guide GAO Schedule Assessment Guide — Best Practices for Project Schedules GAO-16-89G Best Practice 2, Best Practice 4, Best Practice 6, Best Practice 7

ScheduleLens is not affiliated with, endorsed by, or certified by AACE International, the Project Management Institute, the Defense Contract Management Agency, the Chartered Institute of Building, the Society of Construction Law, or the Government Accountability Office. Citations to these standards in this report are bibliographic, indicating the analytical basis for each check.

Produced by ScheduleLens 0.1.0.

22

Appendix A — Reference Standards

Each abbreviation used in the Reference column of the findings table maps to the full title below.

These are bibliographic citations indicating the analytical basis for each check. ScheduleLens is not affiliated with, endorsed by, or certified by AACE International, PMI, DCMA, CIOB, or the Society of Construction Law.

Cited standards
Abbrev.Full title
CIOB CIOB Guide to Good Practice in the Management of Time in Major Projects
AACE AACE International Recommended Practice 29R-03: Forensic Schedule Analysis
DCMA US Defense Contract Management Agency 14-Point Schedule Assessment
SCL Society of Construction Law Delay and Disruption Protocol, 2nd Edition
PMI Project Management Institute — Practice Standard for Scheduling, 2nd Edition, 2011
GAO US Government Accountability Office — Schedule Assessment Guide: Best Practices for Project Schedules (GAO-16-89G), December 2015