Full activity listings and the complete delay register are in
the accompanying Excel appendix.
Disclosures
Analytical tool output — not expert determination
This report is automatically generated from the uploaded schedule file(s). It is an analytical aid — not an expert determination, legal advice, or a certified forensic delay analysis.
Float and criticality are the source scheduling tool's own, as recorded in the file. The tool runs its own calendar-aware critical-path pass to fill a gap where the source recorded no float on incomplete work, and to measure change between two schedules. That pass is an analytical recompute, not a substitute for re-scheduling in P6 or MS Project: it does not level resources, force Expected Finish or imposed-finish dates, or work at sub-day precision. It cannot determine contractual excusability.
Figures should be reviewed by a qualified delay analyst before being relied upon in formal contract correspondence or dispute proceedings. Nothing in this report should be construed as a legal opinion or expert witness statement.
Brief
For the project directorSeverity-coded status headlines, top risks, what to act on.
01
Executive Summary
The schedule health assessment returns an Amber rating, indicating acceptable quality with minor concerns and no critical red flags. The primary finding is the presence of 28 activities with float exceeding 44 working days, which suggests the critical path may not accurately reflect the longest duration path. This structural issue, alongside 13 relationships with positive lag, requires review to ensure the reported dates are reliable for decision-making. The reader should examine the float analysis and relationship checks to verify the integrity of the critical path.
Priority packages:5Top 5 WBS packages by impact score (8 total buckets carry at least one signal).
The Superstructure and MEP Rough-In packages carry the highest impact scores, driven primarily by a concentration of near-critical activities. These areas warrant immediate review to assess the stability of the current schedule logic.
Priority WBS packages
Package
Critical
Warning
Affected
Near-crit.
Top issues
Superstructure
0
1
11
9
Activities with float over 44 working days (2 of 28); Near-critical activities (9 of 25)
MEP Rough-In
0
1
13
6
Activities with float over 44 working days (7 of 28); Near-critical activities (6 of 25)
Building Envelope
0
0
8
7
Activity with duration over 44 working days (1 of 1); Near-critical activities (7 of 25)
Pre-Construction
0
0
1
5
Near-critical activities (1 of 25)
Interior Fit-Out
0
1
4
2
Activities with float over 44 working days (2 of 28); Near-critical activities (2 of 25)
04
Key Milestones
Key milestones:4Auto-detected from the contractual-milestone dictionary, plus critical-path finish milestones as a fallback for custom names.
The contractual and progress dates the project is managed against — Practical Completion, sectional handovers, commissioning — auto-detected and ranked critical-first, lowest float first.
Key milestones — forecast dates and progress
Milestone
Forecast start
Forecast finish
Actual start
Progress
Total float
On critical path
Substructure complete
2026-10-26
2026-10-26
—
0%
0 wd
Yes
Envelope watertight
2027-08-24
2027-08-24
—
0%
0 wd
Yes
Fit-out complete
2028-04-21
2028-04-21
—
0%
0 wd
Yes
Practical Completion
2028-07-03
2028-07-03
—
0%
0 wd
Yes
05
What to do next
2 questions for the programme's author, none critical. In §13: 2 to clarify.
Narrative
For the planner or delay analystSupporting analysis, schedule comparison, driving-path detail.
06
Completion forecast
Completion forecast:Needs your baselineProgramme finish: 2028-07-03.
A forecast needs your baseline programme. Earned Schedule (PMI Standard for EVM, 2019) measures progress against the plan you agreed; run a comparison with your baseline, or track this project, to see it. The programme's own finish is 2028-07-03.
07
Float-path risk
Near-critical paths:8sub-critical or parallel-critical, within 20 working days of the controlling path.
Where else forward risk sits: alternative chains to the project end within 20 working days of the critical path. See Methodology (§21).
8 sub-critical paths within 20 working days of critical — a delay on any of them could shift the controlling path. Rank 1 in the table below is the primary critical path for reference.
Top 3 float paths
#
Float
Activities
Envelope
Driving activity
Branches from
1
0 wd
69
2026-03-02 → 2028-07-03
PRE-140 — Building control approval
—
2
7 wd
69 (1 unique)
2026-03-06 → 2028-07-03
PRE-250 — Site security and CCTV
Path 1 at SUB-110
3
7 wd
35 (8 unique)
2026-10-26 → 2028-07-03
MEP-110 — Main intake and switchgear
Path 1 at FIT-110
Top 3 of 9 paths shown (the primary driving path plus 8 near-critical) — the full 5-path table and the float-path overlay chart are in Float paths — detail; every path is in the Excel appendix.
08
Progress curve
Reading this chart. Two cumulative curves over time: where the schedule should be (Planned Value, solid navy) and where it actually is (Earned Value, solid teal). The vertical dotted line is the data date; the gap between the two curves at that line is the current schedule performance.
Acronyms.
PV (Planned Value): the share of total scheduled work that this schedule's own planned dates put before a given date. It is not your approved baseline, which this file does not carry.
EV (Earned Value): the share actually completed: each activity's original duration multiplied by its percent complete, summed, and divided by the sum of original durations.
SV (Schedule Variance): EV − PV, expressed in working-day equivalents under the duration-weighting.
Progress ratio: EV ÷ PV, here against the schedule's own planned dates. Below 1.00 ⇒ behind those dates; above 1.00 ⇒ ahead.
Not SPI: the progress ratio is not the earned-value SPI (Schedule Performance Index), which is cost-based and measured against an approved baseline. Performance against an approved baseline needs the baseline itself (the completion forecast panel says how).
Why duration-weighted. P6 / MS Project exports routinely strip resource and cost data, so a cost-weighted EV is not always available. Duration-weighting is used instead: each activity contributes in proportion to its original working-day duration rather than its budget. Full formula and caveats: see Methodology (§21).
Duration-weighted progress S-curve
Current plan PV (solid navy) vs actual EV (solid teal). Vertical dotted line marks the data date where the progress ratio is read.
09
Float paths — detail
The full set of near-critical chains behind the Brief-layer float-path callout, with the overlay chart showing when each chain lands on the calendar. The Excel appendix carries the complete per-activity list per path.
Top 5 float paths
#
Float
Activities
Envelope
Driving activity
Branches from
1
0 wd
69
2026-03-02 → 2028-07-03
PRE-140 — Building control approval
—
2
7 wd
69 (1 unique)
2026-03-06 → 2028-07-03
PRE-250 — Site security and CCTV
Path 1 at SUB-110
3
7 wd
35 (8 unique)
2026-10-26 → 2028-07-03
MEP-110 — Main intake and switchgear
Path 1 at FIT-110
4
8 wd
47 (3 unique)
2026-12-03 → 2028-07-03
SUP-210 — Column starter bars L3
Path 1 at SUP-410
5
14 wd
47 (3 unique)
2026-11-13 → 2028-07-03
SUP-310 — Slab L1 formwork
Path 1 at SUP-410
Float-path overlay — when each near-critical chain lands
One bar per top-5 float path showing its divergent window — the activities unique to this path before it merges into a higher-priority chain, with the float window, data date and contractual milestones marked. Reads at a glance: are the alternatives spread across the programme or crowded into one window?
10
DCMA 14-Point compliance — full scorecard
DCMA 14-Point compliance:9 of 11 assessed — 2 fails, 3 not assessed
DCMA 14-Point Assessment: 9 pass, 2 fail, 3 not assessed.
DCMA 14-Point items
Item
Measured
Threshold
Status
Notes
§1 Logic
0.8%
≤5% of incomplete activities
Pass
1 of 131 activities assessed
§2 Leads
0
0 (none allowed)
Pass
0 negative lag(s)
§3 Lags
7.8%
≤5% of relationships
Fail
12 of 154 relationships
§4 Relationship Types
90.9%
≥90% Finish-Start
Pass
140 of 154 are Finish-Start
§5 Hard Constraints
0.0%
≤5% of incomplete activities
Pass
0 hard constraint(s)
§6 High Float
21.4%
≤5% of incomplete activities
Fail
28 activities with > 44 wd float
§7 Negative Float
0
0 (none allowed)
Pass
0 activities with negative float
§8 High Duration
0.8%
≤5% of incomplete activities
Pass
1 activity longer than 44 wd
§9 Invalid Dates
0
0 (none allowed)
Pass
0 activities with dates inconsistent with data date 2026-03-06
§10 Resources
—
Not assessed
PAM 200.1 §4.10: the IMS DID does not require resource loading, so DCMA publishes no canonical threshold for this item
§11 Missed Tasks
—
≤5% of activities with baseline finish on or before status date
Not assessed
schedule has no baseline finish dates
§12 Critical Path Test
Pass
Pass / Fail
Pass
critical activities identified — note this item tests for their presence, not for an unbroken chain to the project finish; see the Open ends section
Cumulative Hit Task Percentage (PAM 200.1 §3.1.2.4 — BEI companion)
—
≥0.95 (informational; PAM publishes no formal threshold)
Not assessed
no activities have baseline finish dates on or before the status date
11
Critical path to Practical Completion
Programme finish target date:2028-07-03 — zero days of slackA slip on an activity below pushes the programme finish date if it sits on a chain that reaches the finish and is not recovered on that same chain. 850 calendar days from the data date.
What controls the project finish date: every activity the source scheduling tool flagged as critical, which on a large programme is many chains.
The 69 activities in this set are flagged as critical by the source scheduling tool's own calendar-aware CPM.
This is the critical set, not a single chain. On a large programme it holds many chains running in parallel — the Gantt below orders them by date, not by logic, so two adjacent rows are usually not linked to each other. A slip on one of them delays the project finish only if it sits on a chain that reaches the finish, and only if it is not offset by acceleration on that same chain. The Critical path sequence chart below traces the single controlling chain end to end, in logic order.
This is the remaining critical set: activities already complete are excluded, because finished work no longer drives the finish date. The cover tile counts the same set. Completed activities that were flagged critical are in the Excel appendix's Critical Path tab.
The critical-path finding in the analysis section reports any material disagreement between this stored set and ScheduleLens' own recalculation.
Critical path rollup — WBS summary bars
One bar per WBS cluster that contains at least one critical or near-critical activity. Bar span is the cluster's envelope (earliest start to latest finish); the count at the right is the number of stored-critical activities in the cluster.
Critical path sequence — the driving chain in order
The driving path to the project endpoint, read in the direction the arrows point, row by row. Each box is a run of consecutive activities on that path sharing a WBS parent (or a single activity on short chains), labelled with how many activities it covers and its date envelope; shading is stage duration. Every activity on the chain is inside exactly one box — nothing is sampled or dropped. This is the same path 1 the float-path table ranks; the critical path rollup above shows the same work against the calendar.
Critical path — activities flagged critical in the source programme
Activities flagged critical by the source scheduling tool, plotted on the project calendar. Bars span the current dates (actual, else forecast). Showing 40 of 69 critical activities; the full list is in the Excel workbook.
12
Float analysis
Float analysis measures how much delay each activity can absorb before it pushes the project finish. Activities with zero or near-zero float drive the completion date.
Float distribution
Distribution of total float across incomplete activities. Very high float (DCMA §6: over 44 working days) may result from missing predecessors or successors; DCMA §7 treats negative float as delaying completion of one or more milestones.
Chart colour key:
Red — activities at immediate risk (negative or zero total float; DCMA §7 counts the negative part)
Amber — activities with 1–10 working days of float
Navy — activities with comfortable float margins
Grey — high float (over 44 working days, the DCMA §6 threshold), which may signal missing logic
Note: the cover-page Near-critical activities headline counts activities within the schedule's status cycle rather than the strict 1–10 wd band, so it can include activities that fall in the amber and navy regions of the chart. See Methodology (§21).
Float distribution (counts)
Bucket
Activities
negative
0
0
69
1-10
10
11-44
28
>44
31
13
What to do next: further questions and recommendations
Questions to clarify
Clarify 1. This link carries a lag: MEP-280 to FIT-160, 15 days into critical work. What does the gap represent? If it is real work, please show it as an activity.
Clarify 2. 1 activity has no predecessor (EXT-310 Boundary fencing). Please link it so the critical path is driven by logic. (§17)
Forensic appendix
Full forensic recordFull evidence, registers, methodology, standards citations.
14
Findings
Findings:13
Each finding below traces to a specific rule in the cited reference standard.
Severity reflects how far the measured value departs from the published target — critical findings indicate the schedule output itself may be unreliable.
Full citations for each abbreviated standard are listed in Appendix A — Reference Standards.
All findings by severity
Severity
Check
Title
Affected
Reference
warning
Float analysis
28 activities with float over 44 working days
SUB-120, SUB-130, SUB-140, SUP-610, SUP-620 (full list in Excel appendix)
DCMA §6 · PMI §3.4.7 · GAO Best Practice 7
warning
Relationships
13 relationships with positive lag
PRE-110 → PRE-210, SUB-110 → SUB-120, ENV-210 → ENV-220, FIT-110 → FIT-120, FIT-120 → FIT-130 (full list in Excel appendix)
The 69 incomplete activities the source scheduling tool flags as critical, ordered by start date. The Critical path section in the Narrative plots them.
Activities on the critical path
ID
Name
WBS
Duration (wd)
Remaining (wd)
Float (wd)
Forecast start
Forecast finish
PRE-140
Building control approval
Permits & Approvals
15
11
0
2026-03-02
2026-03-20
SUB-110
Bulk excavation Zone A
Excavation
17
17
0
2026-03-23
2026-04-16
SUB-210
Piling rig mobilisation
Foundation Piling
10
10
0
2026-04-17
2026-04-30
SUB-220
CFA piling Zone A
Foundation Piling
18
18
0
2026-05-01
2026-05-27
SUB-230
CFA piling Zone B
Foundation Piling
18
18
0
2026-05-28
2026-06-22
SUB-240
Pile integrity testing
Foundation Piling
10
10
0
2026-06-23
2026-07-06
SUB-250
Pile trimming
Foundation Piling
8
8
0
2026-07-07
2026-07-16
SUB-310
Pile cap excavation
Pile Caps & Ground Beams
8
8
0
2026-07-17
2026-07-28
SUB-320
Pile cap reinforcement
Pile Caps & Ground Beams
10
10
0
2026-07-29
2026-08-11
SUB-330
Pile cap concrete pour
Pile Caps & Ground Beams
6
6
0
2026-08-12
2026-08-19
SUB-340
Ground beam install
Pile Caps & Ground Beams
12
12
0
2026-08-20
2026-09-07
SUB-410
Basement slab formwork
Basement Slab
8
8
0
2026-09-08
2026-09-17
SUB-420
Basement slab reinforcement
Basement Slab
12
12
0
2026-09-18
2026-10-05
SUB-430
Basement slab waterproofing
Basement Slab
6
6
0
2026-10-06
2026-10-13
SUB-440
Basement slab pour
Basement Slab
8
8
0
2026-10-14
2026-10-23
MS-SUB-END
Substructure complete
Substructure
0
0
0
2026-10-26
2026-10-26
SUP-110
Column starter bars L1
RC Columns L1-L3
4
4
0
2026-10-26
2026-10-29
SUP-120
Column formwork L1
RC Columns L1-L3
6
6
0
2026-10-30
2026-11-06
SUP-130
Column pour L1
RC Columns L1-L3
4
4
0
2026-11-09
2026-11-12
SUP-140
Column starter bars L2
RC Columns L1-L3
4
4
0
2026-11-13
2026-11-18
SUP-150
Column formwork L2
RC Columns L1-L3
6
6
0
2026-11-19
2026-11-26
SUP-160
Column pour L2
RC Columns L1-L3
4
4
0
2026-11-27
2026-12-02
SUP-340
Slab L2 formwork
Slab Pours L1-L3
8
8
0
2026-12-03
2026-12-14
SUP-350
Slab L2 reinforcement
Slab Pours L1-L3
8
8
0
2026-12-15
2026-12-24
SUP-360
Slab L2 pour
Slab Pours L1-L3
6
6
0
2026-12-29
2027-01-06
SUP-410
Slab L3 formwork
Slab Pours L4-L6
8
8
0
2027-01-07
2027-01-18
SUP-420
Slab L3 reinforcement
Slab Pours L4-L6
8
8
0
2027-01-19
2027-01-28
SUP-430
Slab L3 pour
Slab Pours L4-L6
6
6
0
2027-01-29
2027-02-05
SUP-440
Slab L4 formwork
Slab Pours L4-L6
8
8
0
2027-02-08
2027-02-17
SUP-450
Slab L4 reinforcement
Slab Pours L4-L6
8
8
0
2027-02-18
2027-03-01
SUP-460
Slab L4 pour
Slab Pours L4-L6
6
6
0
2027-03-02
2027-03-09
SUP-510
Roof slab formwork
Roof Slab
10
10
0
2027-03-10
2027-03-23
SUP-520
Roof slab reinforcement
Roof Slab
8
8
0
2027-03-24
2027-04-06
SUP-530
Roof slab pour
Roof Slab
6
6
0
2027-04-07
2027-04-14
ENV-140
Curtain wall install North elevation
Curtain Wall
15
15
0
2027-04-15
2027-05-06
ENV-150
Curtain wall install East elevation
Curtain Wall
15
15
0
2027-05-07
2027-05-27
ENV-160
Curtain wall install South elevation
Curtain Wall
15
15
0
2027-05-28
2027-06-17
ENV-170
Curtain wall install West elevation
Curtain Wall
15
15
0
2027-06-18
2027-07-08
ENV-320
Window install upper floors
Windows & Doors
12
12
0
2027-07-09
2027-07-26
ENV-330
Window install lower floors
Windows & Doors
12
12
0
2027-07-27
2027-08-11
ENV-340
Glazing and seals
Windows & Doors
8
8
0
2027-08-12
2027-08-23
FIT-110
Stud partition L1
Partitions & Ceilings
12
12
0
2027-08-24
2027-09-09
MS-ENV-END
Envelope watertight
Building Envelope
0
0
0
2027-08-24
2027-08-24
FIT-120
Stud partition L2
Partitions & Ceilings
12
12
0
2027-08-31
2027-09-15
FIT-130
Stud partition L3
Partitions & Ceilings
12
12
0
2027-09-06
2027-09-21
FIT-140
Stud partition L4
Partitions & Ceilings
12
12
0
2027-09-10
2027-09-27
FIT-150
Stud partition L5-L6
Partitions & Ceilings
18
18
0
2027-09-16
2027-10-11
FIT-160
Suspended ceilings L1-L3
Partitions & Ceilings
25
25
0
2027-09-16
2027-10-20
FIT-170
Suspended ceilings L4-L6
Partitions & Ceilings
25
25
0
2027-10-21
2027-11-24
FIT-180
Ceiling integration MEP
Partitions & Ceilings
12
12
0
2027-11-01
2027-11-16
FIT-210
Plastering L1-L3
Finishes & Decoration
20
20
0
2027-11-01
2027-11-26
FIT-220
Plastering L4-L6
Finishes & Decoration
20
20
0
2027-11-29
2027-12-24
FIT-240
Painting L4-L6
Finishes & Decoration
18
18
0
2027-12-29
2028-01-21
FIT-260
Floor finishes L4-L6
Finishes & Decoration
22
22
0
2028-01-24
2028-02-22
FIT-310
Reception joinery
Joinery & Fixtures
15
15
0
2028-02-01
2028-02-21
FIT-320
Toilet vanity install
Joinery & Fixtures
18
18
0
2028-02-01
2028-02-24
FIT-330
Tea-point joinery
Joinery & Fixtures
12
12
0
2028-02-08
2028-02-23
FIT-340
Meeting room joinery
Joinery & Fixtures
18
18
0
2028-02-24
2028-03-20
FIT-350
Built-in storage and fittings
Joinery & Fixtures
15
15
0
2028-03-21
2028-04-10
FIT-360
Final joinery snagging
Joinery & Fixtures
8
8
0
2028-04-11
2028-04-20
CMS-210
Client walkthrough and snag list
Snagging & Punchlist
5
5
0
2028-04-21
2028-04-27
MS-FIT-END
Fit-out complete
Interior Fit-Out
0
0
0
2028-04-21
2028-04-21
CMS-220
Major snags rectification
Snagging & Punchlist
15
15
0
2028-04-28
2028-05-18
CMS-230
Minor snags rectification
Snagging & Punchlist
12
12
0
2028-05-19
2028-06-05
CMS-240
Final inspection
Snagging & Punchlist
4
4
0
2028-06-06
2028-06-09
CMS-310
Building handover documentation
Practical Completion
8
8
0
2028-06-12
2028-06-21
CMS-320
O&M manuals issued
Practical Completion
4
4
0
2028-06-22
2028-06-27
CMS-330
Soft landings start
Practical Completion
3
3
0
2028-06-28
2028-06-30
MS-PC
Practical Completion
Practical Completion
0
0
0
2028-07-03
2028-07-03
16
Logic quality
Logic quality checks assess whether the network is fully driven by sequential dependencies. Gaps, excessive non-FS links, and dangling chains all undermine the critical path calculation.
Relationship type distribution
Type
Count
FS
166
SS
14
FF
0
SF
0
Total
180
FS ratio
92.2%
Open ends
Finding
Count
1 activity with no predecessor
1
Other logic-quality findings
Check
Count
Redundant relationships
5
17
Open ends
Activities with missing logic — either no predecessor (nothing must happen before them) or no successor (nothing depends on their completion).
DCMA 14-Point §1 expects fewer than 5% of incomplete activities to have open logic.
Missing predecessors allow an activity to start on the project start date regardless of its true sequencing.
Missing successors mean delay to the activity never flows through to the completion date.
Review each row and confirm with the planner whether the logic gap is intentional.
Activities with open logic
ID
Name
WBS
Issue
Duration (wd)
Float (wd)
EXT-310
Boundary fencing
Boundary Treatments
No predecessor
12
122
18
Schedule metadata
Source and calculation
Field
Value
Source format
xer
Data date
2026-03-06
Project start
2026-01-05
Project finish
2028-07-03
Activities
149
Relationships
180
Calendars
1
Scheduling options read from the source file. These govern how the source scheduling tool calculated float and the critical path.
Two options in particular (Progress Override and 'Make open-ended activities critical') can change the reported critical path materially without changing a single activity or relationship.
Any setting that warrants a warning is listed separately in the Findings table above.
Scheduling options
Option
Value
Retained Logic
Yes (ON)
Progress Override
No (OFF)
Make open-ended activities critical
No (recommended)
Float type
Finish Float
External-project dependency handling
Apply external dates to both start and finish
Use Expected Finish dates
Yes
Lag from predecessor early start
Yes
Calendar used for relationship lag
Predecessor calendar
Source file
Field
Value
P6 version
19.12
Export date
2026-03-06
19
DCMA detail — offending activities
The activities and relationships behind each failing DCMA item, most severe first. Tables are capped at 20 rows; the Excel appendix's “DCMA detail” sheet carries the full lists.
§3 Lags — 12 of 154 relationships
Ref
Name
Value
MEP-280 → FIT-160
Insulation and labelling → Suspended ceilings L1-L3
Cladding survey and setting-out → Cladding North elevation
SS lag +5 wd
FIT-320 → FIT-330
Toilet vanity install → Tea-point joinery
SS lag +5 wd
FIT-110 → FIT-120
Stud partition L1 → Stud partition L2
SS lag +4 wd
FIT-120 → FIT-130
Stud partition L2 → Stud partition L3
SS lag +4 wd
FIT-130 → FIT-140
Stud partition L3 → Stud partition L4
SS lag +4 wd
FIT-140 → FIT-150
Stud partition L4 → Stud partition L5-L6
SS lag +4 wd
SUP-330 → SUP-440
Slab L1 pour → Slab L4 formwork
SS lag +2 wd
§6 High Float — 28 activities with > 44 wd float (showing 20 of 28 — full list in the Excel appendix)
Ref
Name
Value
EXT-110
External drainage
123 wd float
EXT-120
Sub-base preparation
123 wd float
EXT-130
Tarmac surfacing
123 wd float
EXT-140
Line marking and signage
123 wd float
EXT-210
Soft landscape preparation
123 wd float
EXT-220
Planting and turf
123 wd float
EXT-230
Hard landscape features
123 wd float
EXT-310
Boundary fencing
122 wd float
EXT-320
Gates and access controls
122 wd float
MEP-355
Additional fire-water tank install
120 wd float
MEP-320
Riser plumbing
109 wd float
MEP-330
Floor plumbing L1-L3
109 wd float
MEP-340
Floor plumbing L4-L6
109 wd float
MEP-350
Sprinkler mains
109 wd float
MEP-360
Sprinkler floor distribution
109 wd float
SUP-610
Roof waterproofing membrane
78 wd float
SUP-620
Roof finishes and parapet
78 wd float
MEP-110
Main intake and switchgear
71 wd float
FIT-230
Painting L1-L3
62 wd float
FIT-250
Floor finishes L1-L3
62 wd float
20
Excel appendix guide
The accompanying .xlsx workbook is the audit companion to this PDF. Wherever the PDF says full list in Excel appendix, the matching tab below carries the unabridged data.
The workbook is laid out in two tiers. The first tier (presentation tabs) gives audit-ready tables of milestones, the critical path, ranked float paths, and the full activity register. The second tier (findings-register tabs) drills into each individual finding with affected activities — one tab per finding.
Tier 1 — presentation tabs
Tab
Contents
Summary
Schedule metadata (project dates, activity count) plus every finding with severity, count, and reference. The row to start at when triaging the report.
Key Milestones
The full set of detected key milestones with the detection rationale spelled out (contractual keyword, user-supplied keyword, or critical-path WBS-tail fallback). The PDF body is capped at 15; this tab is uncapped.
Critical Path
Every activity flagged critical by the source scheduling tool, complete and incomplete. The PDF Critical-path section filters to incomplete-only for clarity; this tab is the unfiltered companion.
Float Paths
Every ranked near-critical chain — the full list behind the PDF Float-path risk section's top-5 table. Includes the activity sequence comma-separated for search.
Activities
Every activity in the schedule with predecessors and successors inline. The audit substrate — whatever the PDF Findings table references, look up the activity row here to see its surrounding logic.
DCMA detail
The full offender lists behind each failing DCMA item — one block per check, most severe first. The PDF's DCMA detail appendix caps at 20 rows per check; this tab is uncapped. Present only when at least one item fails.
Tier 2 — findings-register tabs
Tab
Contents
Float over threshold
Activities with total float above DCMA §6's 44-day threshold, which may result from missing predecessors or successors.
Lags
Every relationship with a positive lag, with both activities named.
Long-duration activities
Activities with planned duration above DCMA §8's 44-day threshold — candidates to break down further.
Near-critical activities
Activities within the schedule's status-cycle float band.
Open ends - no predecessor
Incomplete activities with no predecessor — they will start on the project start date regardless of true sequencing.
Redundant relationships
Finish-to-Start relationships another path already drives, with both activities named.
These are the register tabs this analysis produced. The list is derived from the findings themselves, so it matches the workbook exactly rather than describing every tab the tool can emit.
21
Methodology
This report assesses the uploaded schedule against the published industry standards listed below. Each finding traces to a specific rule in one or more of those standards. The analysis is automated and deterministic — the same schedule file will always produce the same findings.
Scope of this analysis. This report is based solely on the schedule file you uploaded. Two conventions govern how its figures were derived, and both matter when reconciling them against the source tool:
Date basis. Every start and finish date in this report is each schedule's *current forecast* — the date work is now expected to occur, or its recorded actual date where the work is complete. In Primavera P6 that is the Remaining Early date; in Microsoft Project and Asta Powerproject it is the scheduled Start/Finish. The report does not use a tool's frozen Planned/target dates, which stop updating once an activity is in progress and so understate movement on a progressed schedule. Baseline dates stored inside a file (e.g. a P6 baseline) are read as recorded, and every variance compares the current forecast on each side.
Float and criticality — the source tool's — every total-float and critical-path figure in this report (including the DCMA float checks, float paths, near-critical detection and milestone deliverability) is the value recorded by the scheduling tool that produced the file. ScheduleLens does not overwrite it. Where the source recorded no float and the activity is incomplete, ScheduleLens's own calendar-aware pass supplies one; completed activities are left unfloated rather than given an invented value. That gap-filling pass applies Retained Logic/Progress Override per the file's scheduling options but does not model Start/Finish-No-Later-Than or As-Late-As-Possible constraints, Expected Finish forcing, or an imposed must-finish date. ScheduleLens's own critical-path pass is used for change between two schedules — critical-path churn, bounded what-if, retained-logic versus progress-override, between-snapshot slip — where both sides run through the same engine; those figures are labelled as ScheduleLens's. Where the independent pass disagrees with the file's own critical flags, the disagreement is reported by the critical-path staleness check rather than resolved.
Units. Day figures in this report are calendar days unless they are marked as working days. Two different quantities are being measured and the distinction is deliberate.
Movement between two dates — how far completion, a milestone or the schedule end has moved between submissions — is reported in calendar days. Elapsed time is the same quantity for every activity on a programme, so figures measured this way can be compared with each other, and they do not change when a calendar's holidays are edited. AACE RP 29R-03 directs that as-built comparison be carried out in calendar days for this reason, and cautions that float expressed in workday units differs between activities on different calendars; SCL Protocol §8.8 gives the same caution where multiple work-day calendars are in use.
Schedule properties — float, activity durations, the delay quantum recorded against each event, and the DCMA thresholds — are reported in working days, and are marked as such wherever they appear. These are not spans between two dates and have no calendar-day equivalent: an activity whose duration grows from 10 to 20 working days has no single elapsed-day value, because that depends on where in the calendar the work falls. The DCMA 14-point checks define their thresholds in working days, so restating them would change what is being tested.
A working-day figure is counted on the calendar assigned to the activity it describes, not on the project default — on a programme running five-day and seven-day calendars together, the same elapsed period is a different number of working days for different activities.
Near-critical threshold. Float paths and the near-critical count use a threshold set by the schedule's status cycle, not its length: the question is whether an activity could become controlling, with a small slip, before the next status update. The default is 20 working days, a monthly cycle; it can be set for each project at upload. No published standard prescribes a value. The float distribution chart keeps the DCMA bands (1–10, 11–44 and over 44 working days) so its shape compares across reports, which is why the near-critical count can include activities in the 11–44 band.
Duration-weighted progress. Exported schedules rarely carry cost or resource loading, so the progress curve weights each activity by its original duration. Planned value (PV) at a date is the share of that weighted work the schedule's own planned dates put before it. Earned value (EV) is each activity's original duration multiplied by its percent complete, summed, and divided by the sum of original durations. Summary, level-of-effort and milestone activities are excluded. The progress ratio (EV ÷ PV) is measured against the file's planned dates, not an approved baseline, so it is not the earned-value SPI.
Use of AI. The ScheduleLens analysis engine computed every finding, figure, score and chart in this report. At the requester's election, a language model (qwen3-6-27b, via Venice) then wrote the explanatory prose in the sections “Executive Summary” and “Where to focus first”. It worked only from those computed results. It did not see the schedule file and did no analysis of its own. Where prose and a table or chart differ, the table or chart governs.
Standards referenced
Short name
Full title
Edition
Sections cited
DCMA 14-Point
DCMA EVMS Program Analysis Pamphlet (PAM) — §4 14 Point Schedule Metrics for IMS Analysis
GAO Schedule Assessment Guide — Best Practices for Project Schedules
GAO-16-89G
Best Practice 2, Best Practice 4, Best Practice 6, Best Practice 7
ScheduleLens is not affiliated with, endorsed by, or certified by AACE International, the Project Management Institute, the Defense Contract Management Agency, the Chartered Institute of Building, the Society of Construction Law, or the Government Accountability Office. Citations to these standards in this report are bibliographic, indicating the analytical basis for each check.
Produced by ScheduleLens 0.1.0.
22
Appendix A — Reference Standards
Each abbreviation used in the Reference column of the findings table maps to the full title below.
These are bibliographic citations indicating the analytical basis for each check. ScheduleLens is not affiliated with, endorsed by, or certified by AACE International, PMI, DCMA, CIOB, or the Society of Construction Law.
Cited standards
Abbrev.
Full title
CIOB
CIOB Guide to Good Practice in the Management of Time in Major Projects
AACE
AACE International Recommended Practice 29R-03: Forensic Schedule Analysis
DCMA
US Defense Contract Management Agency 14-Point Schedule Assessment
SCL
Society of Construction Law Delay and Disruption Protocol, 2nd Edition
PMI
Project Management Institute — Practice Standard for Scheduling, 2nd Edition, 2011
GAO
US Government Accountability Office — Schedule Assessment Guide: Best Practices for Project Schedules (GAO-16-89G), December 2015