The DCMA 14-Point schedule check

A plain-English reference to the 14 checks the US Defense Contract Management Agency uses to test schedule quality — what each one looks for, and the standard target.

A schedule that passes these is structurally sound. It says nothing about whether the plan is realistic — that is judgement — but failures here are where most weak programmes give themselves away. Run all 14 before you trust a programme you have been handed.

# Check What it looks for DCMA target
1 Logic Incomplete tasks missing a predecessor and/or successor < 5%
2 Leads Negative lag on relationships 0
3 Lags Relationships carrying a lag < 5%
4 Relationship types Share of relationships that are Finish-to-Start ≥ 90%
5 Hard constraints Tasks with a hard (date) constraint < 5%
6 High float Incomplete tasks with total float > 44 working days < 5%
7 Negative float Tasks with total float below zero 0
8 High duration Incomplete tasks with a baseline duration > 44 working days < 5%
9 Invalid dates Forecast dates before, or actual dates after, the data date 0
10 Resources Tasks with duration but no resource/cost (if resource-loaded) 0
11 Missed tasks Tasks that should have finished by the data date but haven't < 5%
12 Critical path test A continuous, intact critical path exists Pass
13 CPLI Critical Path Length Index Realism of the critical path to the finish ≥ 0.95
14 BEI Baseline Execution Index Tasks completed versus the baseline plan ≥ 0.95

Targets are the conventional DCMA thresholds. The “44 working days” limits on float and duration map to a two-month planning horizon.

Working through all 14 by hand on a 5,000-activity programme takes a while. ScheduleLens scores them automatically from a Primavera P6, Asta Powerproject, or MS Project file — but the checklist stands on its own, so keep it.

Score a real schedule against all 14

Upload a programme and get the DCMA scorecard in your report, in minutes.