ScheduleLens Demo — Commercial Office Construction

5 snapshots · ordered by schedule data date

+ Add snapshot Rename

Programme finish

ⓘ

22 Jun 2028

Earned Schedule finish: 12 Apr 2029 (9 months 20 days later)

DCMA compliance

ⓘ

9 / 14

Watch

3 fails, 2 not assessed

Remaining duration to completion (wd)

ⓘ

705

+2 since prior

Activities at risk

ⓘ

44

+1 since prior

Float ≤ 20 wd or negative

Trend across snapshots

Grouped by what each metric is measured against.

Absolute · each schedule on its own

DCMA score

9 / 14

10 / 14 → 9 / 14 across 5 snapshots

Earned Schedule finish vs programme finish

9 months 20 days later

Remaining duration to completion (wd)

705 wd

vs Baseline · the plan of record

BEI

0.88

Float consumed (wd)

6 wd

1 period excluded (re-baseline / re-sequence — comparison limited)

Concealed slip (wd)

ⓘ

35 wd

The live dashboard also carries a vs Prior month group (per-period moves as signed bars off a zero line). Trimmed here for the sample.

Scheduling mode changed mid-monitoring

  • Retained logic → Progress override at 8 Apr 2026 — figures from this snapshot on may understate slippage.

Progress Override discards predecessor logic for in-progress activities; the critical path, float, and forecast can differ materially from the same file scheduled under Retained Logic.

Data date Type Programme finish DCMA CP (wd) At risk Baseline BEI (vs baseline) Float used (vs baseline, median wd) Concealed slip (vs baseline, wd)
5 Jan 2026
Baseline Retained logic
8 Jun 2028
10 / 14 685 34 Baseline · default — — —
6 May 2026
Comparison Progress override
22 Jun 2028
ES ⇒ 12 Apr 2029
9 / 14 705 44 Set 0.88 6 35
8 Apr 2026
Comparison Progress override
22 Jun 2028
ES ⇒ 18 Feb 2029
9 / 14 703 43 Set 0.90 limited 28
6 Mar 2026
Comparison Retained logic
22 Jun 2028
ES ⇒ 5 Dec 2028
9 / 14 702 41 Set 0.92 19 12
4 Feb 2026
Comparison Retained logic
15 Jun 2028
ES ⇒ 20 Aug 2028
10 / 14 690 36 Set 0.97 8 —

On the live dashboard, clicking a row opens that snapshot's full analysis report, and each row carries Forget / Detach / Delete controls (trimmed from this sample).

Ask about this project

Subscriber feature

A grounded, read-only assistant that answers from the computed results across every snapshot — it never guesses.

How does the programme's finish compare with the progress trend?
The programme's own finish moved from 8 Jun 2028 at baseline to 22 Jun 2028 at Update 4. Earned Schedule, our measure of progress against the baseline, is much later: it moved from 20 Aug 2028 (Update 1) to 12 Apr 2029 (Update 4), about 9 months 20 days after the programme's date. Two signals sit underneath the gap: BEI fell from 0.97 to 0.88 (work is completing slower than planned), and at Update 3 the programme switched to Progress Override, after which concealed slip climbed to 35 working days as activity durations were shaved.
Ask about this project… Send

What this dashboard tells you

  • The programme's finish moved two weeks, but progress against the baseline points to April 2029. The programme still shows 22 Jun 2028, while the Earned Schedule finish moved from 20 Aug 2028 to 12 Apr 2029 across four monthly updates. A gap that size is the question to put to the contractor at the next progress meeting.
  • The programme switched to Progress Override at Update 3. That P6 setting discards predecessor logic for in-progress activities, so the critical path, float, and forecast can understate real slippage from that point on.
  • Concealed slip climbed to 35 working days. Restoring each activity's duration to the baseline value and recomputing shows the forecast is later than the dates alone admit — slip hidden by shaved durations.
  • BEI fell from 0.97 to 0.88 while DCMA quality held at 9 / 14. The structural quality is steady; the problem is delivery pace and how the slippage is being presented, not schedule hygiene.

On a real Project dashboard, clicking any row opens the underlying analysis report. Try the sample Health report, Comparison report, or Series report.

The Project dashboard is included with every ScheduleLens subscription — from $79/month (Single Project).